Final | 5/5/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by David McClellan Outlet upstairs by sink was replaced with GFI. Ok final
|
Final | 4/17/2017 | 4/18/2017 | 4/18/2017 | P | CANC |
Mark Moncarr
|
|
|
Both 926 and 928 units of duplex to be finaled please. Phone #: ###-#### >> Inspection requested via web by David McClellan Inspection cancelled from web by: David McClellan
|
Final | 4/17/2017 | 4/18/2017 | 4/17/2017 | A | CANC |
Mark Moncarr
|
|
|
Final on each side of the duplex, both 926 and 928 N. 32nd St. Phone #: ###-#### >> Inspection requested via web by David McClellan Inspection cancelled from web by: David McClellan
|
Conference | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | DONE |
Mark Moncarr
|
|
|
Consultation requested around 10am if possible. Please call me. This regarding the homeowner wanting to move/add a dual meter pack now AFTER I was instructed to separate them to 2 for townhouse scenario after having the dual orignarly mounted. Phone #: ###-#### Inspection requested via web by David McClellan Talked about previous discussions about service disconnect locations
|
Electrical Rough-In | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | PASS |
Mark Moncarr
|
|
|
Heated bathroom floor rough-in on north side unit. Phone #: ###-#### Inspection requested via web by David McClellan ok cover
|
Electrical Rough-In | 1/19/2017 | 1/20/2017 | 1/20/2017 | P | PASS |
Tom Saunders
|
|
|
Heated bathroom floors roughed in and ohm tested. Both sides Phone #: ###-#### Inspection requested via web by David McClellan
ok to cover
|
Electrical Rough-In | 1/17/2017 | 1/17/2017 | 1/18/2017 | P | DONE |
Mark Moncarr
|
|
|
This inspection is 4 the bathroom heated floors pre inspection to ensure dedicated circuits 2 the bathrooms for that purpose and for inspection only Phone #: ###-#### Inspection requested via web by David McClellan Dedicated circuits for floor heat locations.
|
Electrical Rough-In | 1/14/2017 | 1/17/2017 | 1/15/2017 | A | CANC |
Mark Moncarr
|
|
|
All 6 bathroom''s in 926, 928 are getting heated floors. Requesting floor inspection prior to install of floor wiring. Phone #: ###-#### >> Inspection requested via web by David McClellan Inspection cancelled from web by: David McClellan
|
Electrical Rough-In | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Mark Moncarr
|
|
|
2 sides duplex/ townhome Phone #: ###-#### Inspection requested via web by David McClellan p/s u/g n ok. Ok cover both sides, energize service on south side only
|
Conference | 9/9/2016 | 9/12/2016 | 9/12/2016 | A | DONE |
Rock A. Hudson
|
|
|
Bldg will be zoned townhouse in future. Need to consult to determine best move forward. Phone #: ###-#### Inspection requested via web by David McClellan Discussed wiring as townhouses so all shall be seperated as 2 seperate dwellings. No penatrations in center firewall.
|
Rough-In Permanent Service | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | FAIL |
Rock A. Hudson
|
|
|
David ###-####. Need to check requirements for townhouse property lines due to notes on building permit. With notes for build as townhouses seperate services are required. Contractor scheduled conference for Monday.
|
Rough-In Permanent Service | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | NR |
Rock A. Hudson
|
|
|
Dual 200 meter base ; grounding. Phone #: ###-#### Inspection requested via web by David McClellan Will reschedule for 9-9-16. Location of service will be in conflict if rezoned for town houses it is located on what would be property line and dividing wall. No penetrations in 2 hour firewall.
|
Rough-In Permanent Service | 9/2/2016 | 9/6/2016 | 9/6/2016 | A | CANC |
Mark Moncarr
|
|
|
Phone #: ###-#### >> Inspection requested via web by David McClellan Inspection cancelled from web by: David McClellan
|