Final | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...
ok to final
|
Final | 12/13/2016 | 12/14/2016 | 12/14/2016 | P | PART |
Tom Saunders
|
|
|
Temporary final Phone #: ###-#### Inspection requested via web by Tom Jenkins...
90 percent complete....left to check front desk reception counter outlets LV openings procedure lights work station cutin outlets cut in in physical therapy check exit signs lockout on dishwasher
|
Electrical Rough-In | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Tom Saunders
|
|
|
Ceiling rough in. Phone #: ###-#### Inspection requested via web by Tom Jenkins...
ceiling ok to cover
|
Conference | 11/30/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...
discussed support wires for luminaires, quantity on led lights, earhquake clips, places can install ceiling tiles...leave areas open that feel need inspected
|
Electrical Rough-In | 10/31/2016 | 10/31/2016 | 10/31/2016 | P | PASS |
Tom Saunders
|
|
|
soffit ceiling/hard lid areas...bathrooms, dropped soffits, halwways....ok to cover
|
Electrical Rough-In | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | CANC |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins Inspection was done on proir date
|
Electrical Rough-In | 10/21/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Tom Saunders
|
|
|
wall cover ok
|