Final | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Gehring final ok
|
Final | 10/5/2016 | 10/6/2016 | 10/6/2016 | P | NR |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Gehring need water in hottub to test GFI brkr.
|
Final | 10/3/2016 | 10/5/2016 | 10/5/2016 | P | CANC |
Mark Moncarr
|
|
|
I would like to have this inspection around 1 pm, so Idaho Power can reconnect for Wednesday evening. Phone #: ###-#### Inspection requested via web by Ryan Gehring Permit is for p/s rec. Once other additional work is done, contractor was notified to call in for a final once finished.
|
Permanent Service | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PASS |
Mark Moncarr
|
|
|
p/s u/g rec ok. Changed from final to p/s. Let contractor know that when his hottub is done to call service and extra work in for a final.
|