Final | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Mark Moncarr
|
|
|
Gary is the contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Ok final
|
Electrical Rough-In | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PASS |
Mark Moncarr
|
|
|
We need a ceiling inspection. Thank you Inspection requested via web by Stacie Tasker Ok cover ceiling.
|
Permanent Service | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PASS |
Mark Moncarr
|
|
|
Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker p/s u/g n ok
|
Electrical Rough-In | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PASS |
Mark Moncarr
|
|
|
We need a wall cover. Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Ok cover all walls
|
Electrical Rough-In | 3/29/2017 | 3/29/2017 | 3/29/2017 | A | PASS |
Mark Moncarr
|
|
|
We need a ceiling cover. Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Ok cover drive thru canopy and 2 outer soffits
|
Electrical Rough-In | 12/1/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Mark Moncarr
|
|
|
WE need and underground inspection. Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ok cover
|
Electrical Rough-In | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Mark Moncarr
|
|
|
We need an underground inspection, Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ok cover
|
Electrical Rough-In | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | PASS |
Mark Moncarr
|
|
|
We need a uffer inspection for today, Travis is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ufer ok cover
|