Final | 8/30/2017 | 8/30/2017 | 8/30/2017 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins....
job complete....full final...sign power done by others...pipe and junction box only supplied by contractor
|
Final | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PART |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins....
rooms 101-126, north corridor, porta cache, entry...ok to final
|
Electrical Rough-In | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...
needed to schedule as final to do partial...see final notes
|
Final | 8/17/2017 | 8/17/2017 | 8/17/2017 | A | PART |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...
partial final...south rooms 149-134, 127-133...corridor up to rm 133 and south corridor minus panels...need schedules
|
Electrical Rough-In | 7/11/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Tom Saunders
|
|
|
Kitchen Phone #: ###-#### Inspection requested via web by Bryan Atkins...
full rough complete...areas marked on plans
|
Electrical Rough-In | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PASS |
Tom Saunders
|
|
|
Dining, activity, barista, salon Phone #: ###-#### Inspection requested via web by Bryan Atkins..
junction boxes over offices complete, areas as marked dated on plans...ok to cover
|
Permanent Service | 6/14/2017 | 6/15/2017 | 6/15/2017 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...
p/s u/g n ok
|
Electrical Rough-In | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Tom Saunders
|
|
|
Laundry room, break room, etc. Phone #: ###-#### Inspection requested via web by Bryan Atkins...
ok to cover areas marked and dated on plans...check junction boxes above offices once wired pulled...verify made up and labelling
|
Electrical Rough-In | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Tom Saunders
|
|
|
North Corridor Phone #: ###-#### Inspection requested via web by Bryan Atkins....
corridors ok to cover...marked on plans
|
Electrical Rough-In | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Tom Saunders
|
|
|
Rough-in Courtyard soffit, electrical room wall Phone #: ###-#### Inspection requested via web by Bryan Atkins...
areas marked on plans...ok to cover
|
Electrical Rough-In | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Eric Story
|
|
|
Soffit Lights Phone #: ###-#### Inspection requested via web by Bryan Atkins Soffits only on perimeter siffts ok cover
|
Electrical Rough-In | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Tom Saunders
|
|
|
NW Units Phone #: ###-#### Inspection requested via web by Bryan Atkins...
all resident rooms and rooms as marked on plans...ok to cover
|
Electrical Rough-In | 4/17/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Tom Saunders
|
|
|
Partial r-in rooms / corridor Phone #: ###-#### Inspection requested via web by Bryan Atkins...
ok to cover rooms and corridors as marked on plans
|
Electrical Rough-In | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Tom Saunders
|
|
|
Partial R/I for rooms to be ok to cover Phone #: ###-#### Inspection requested via web by Bryan Atkins...
rough ok to cover SE exterior rooms-10 as marked on plans
|
Electrical Rough-In | 4/6/2017 | 4/6/2017 | 4/6/2017 | P | CANC |
Tom Saunders
|
|
|
R/I partial rooms for ok to cover Phone #: ###-#### >> Inspection requested via web by Bryan Atkins Inspection cancelled from web by: Bryan Atkins
|
Electrical Rough-In | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PASS |
Rock A. Hudson
|
|
|
R/I Underground Poles Phone #: ###-#### Inspection requested via web by Bryan Atkins Front pole bases and underground rough in ok cover
|
Electrical Rough-In | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | CANC |
Rock A. Hudson
|
|
|
U/G Poles Phone #: ###-#### >> Inspection requested via web by Bryan Atkins Inspection cancelled from web by: Bryan Atkins
|
Electrical Rough-In | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | PASS |
Tom Saunders
|
|
|
U/G inspection Phone #: ###-#### Inspection requested via web by Bryan Atkins...
u/g and parking lot light bases
|
Electrical Rough-In | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | PASS |
Tom Saunders
|
|
|
Service Laterals U/G inspection Phone #: ###-#### Inspection requested via web by Bryan Atkins...
ok to cover
|
Electrical Rough-In | 11/3/2016 | 11/3/2016 | 11/3/2016 | P | PASS |
Tom Saunders
|
|
|
underground inspection done on october 31st...canceled by accident...ok
|
Electrical Rough-In | 10/31/2016 | 10/31/2016 | 10/31/2016 | P | CANC |
Tom Saunders
|
|
|
underground Phone #: ###-#### Inspection requested via web by Bryan Atkins...ok to cover
|