Final | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PASS |
Rock A. Hudson
|
|
|
9th floor elevator lobby and bathroom Phone #: ###-#### Inspection requested via web by steve ragan Contractor provided ladder to check areas noted for ceiling rough...OK. Final ok
|
Electrical Rough-In | 12/22/2016 | 12/22/2016 | 12/22/2016 | P | FAIL |
Rock A. Hudson
|
|
|
Inspect can light frame rough-in and installed strip lighting in elevator lobby and halls. 9th floor Phone #: ###-#### Inspection requested via web by steve ragan BCC 4-05-32- code violations not to be retained. 300.15- All splice point shall be contained in a box. 314.25- All boxes shall have covers installed. 358.30- Support for existing conduits has been removed at some point. Each Emt conduit shall be supported with in 3' of a box and shall have supports not to exceed 10' between.
|
Electrical Rough-In | 12/9/2016 | 12/12/2016 | 12/12/2016 | A | PASS |
Rock A. Hudson
|
|
|
Can light frames rough-in in bathroom vestibules on 9th floor. Phone #: ###-#### Inspection requested via web by steve ragan Bathroom entrance ceilings rough in ok cover
|