Final | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | PASS |
Tom Saunders
|
|
|
Inspection per Justin''s conversation. Phone #: ###-#### Inspection requested via web by A.M.E. Office...
ok to final...pics of working fixture
|
Final | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | CANC |
Tom Saunders
|
|
|
scheduled to get contractors number
|
Final | 12/20/2016 | 12/20/2016 | 12/20/2016 | P | FAIL |
Tom Saunders
|
|
|
Please contact Art Solis for access to the building. Phone #: ###-#### Inspection requested via web by A.M.E. Office...
1) one flourescent light is not operational 110.3
2) approved plans from Boise City show exit and emergency signs shall be wired in to building...non of that work has been done.
|
Electrical Rough-In | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Tom Saunders
|
|
|
ROUGH IN INSPECTION FOR THE CLASSROOM AND BATHROOMS. JUSTIN CAN ANSWER ANY QUESTIONS. THANK YOU Phone #: ###-#### Inspection requested via web by A.M.E. Office....
rough ok to cover
|