Final | 2/1/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Debby Pierce No card posted, asked if needed occupancy card signed and informed on line will be fine. Final ok
|
Final | 1/29/2018 | 1/30/2018 | 1/30/2018 | P | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Debby Pierce Pay stations in stair towers not set yet. 300.15- All wiring shall terminate in a box.
|
Final | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PART |
Rock A. Hudson
|
|
|
Final TOC Level 1 excludes stairwells, Elevator, and Generator Phone #: ###-#### Inspection requested via web by Debby Pierce Level 1 of parking garage only partial final ok
|
Permanent Service | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Rock A. Hudson
|
|
|
Available Fault current at MC 62,561 Inspection requested via web by Debby Pierce p/s u/g n ok
|
Permanent Service | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | FAIL |
Rock A. Hudson
|
|
|
110.24- Available fault current shall be posted prior to permenant service inspection. George will call with value, sticker on meter. 64k rated main breakers installed.
|
Electrical Rough-In | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Rock A. Hudson
|
|
|
STR B Landings Phone #: ###-#### Inspection requested via web by Debby Pierce Rough in for stair B pour rough in ok cover
|
Electrical Rough-In | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Rock A. Hudson
|
|
|
L5 Deck pour 20 ; 21 rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Areas noted rough in ok cover
|
Electrical Rough-In | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PASS |
James Ady
|
|
|
L5 deck pour 19.
L1 South side underground, pole bases Phone #: ###-#### Inspection requested via web by Debby Pierce Areas listed ok to cover
|
Electrical Rough-In | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Rock A. Hudson
|
|
|
L4 deck pour 18 rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Rock A. Hudson
|
|
|
L4 deck pour 17 ramp Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 9/15/2017 | 9/15/2017 | 9/15/2017 | P | PASS |
Rock A. Hudson
|
|
|
L5 deck rough-in. Phone #: ###-#### Inspection requested via web by Debby Pierce Contractor to adjust valuation for additional level added and the new location of service for building. Level 5 pour 16 and underground for service next to transformer and to sub fed building rough in ok cover
|
Electrical Rough-In | 8/11/2017 | 8/11/2017 | 8/11/2017 | P | PASS |
Rock A. Hudson
|
|
|
L3 Deck Pour 15B Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Rock A. Hudson
|
|
|
L3 deck pour 15A Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PASS |
Rock A. Hudson
|
|
|
L3 deck pour 13 ; 14 rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce General contractor asked to check in office before each inspection. Area noted rough in ok cover
|
Electrical Rough-In | 7/7/2017 | 7/7/2017 | 7/7/2017 | P | PASS |
Rock A. Hudson
|
|
|
L3 deck pour 12 Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted which is ramp rough in ok cover
|
Electrical Rough-In | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
James Ady
|
|
|
L3 deck pour 11 Phone #: ###-#### Inspection requested via web by Debby Pierce ok to cover
|
Electrical Rough-In | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PASS |
Rock A. Hudson
|
|
|
L2 Deck pour 10B Phone #: ###-#### Inspection requested via web by Debby Pierce Level 2 pour 9 and 10(B) rough in ok cover
|
Electrical Rough-In | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Rock A. Hudson
|
|
|
L2 deck pour 10 Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Rock A. Hudson
|
|
|
L1 RCU''S Col. D11 underground rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Level 1 underground as noted and added level 2 pour 8 rough in ok cover
|
Electrical Rough-In | 5/5/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Rock A. Hudson
|
|
|
L2 Deck pour 7 rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 5/3/2017 | 5/4/2017 | 5/4/2017 | A | PASS |
Rock A. Hudson
|
|
|
L2 Deck pour 6 rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 4/21/2017 | 4/21/2017 | 4/21/2017 | P | PASS |
Rock A. Hudson
|
|
|
L1 pour 5B rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Rock A. Hudson
|
|
|
L1 deck pour 5A rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PASS |
Rock A. Hudson
|
|
|
L1 Deck pour 4 Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | PASS |
James Ady
|
|
|
L1 deck pour 3 Phone #: ###-#### Inspection requested via web by Debby Pierce ok to cover
|
Electrical Rough-In | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Rock A. Hudson
|
|
|
L1 Pour 2 Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Temporary Service | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | FAIL |
Rock A. Hudson
|
|
|
Temp service for Decks Phone #: ###-#### Inspection requested via web by Debby Pierce new permit required for new metered temp service
|
Electrical Rough-In | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Rock A. Hudson
|
|
|
L1 Deck rough-in / Pour 1 Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 3/7/2017 | 3/7/2017 | 3/7/2017 | A | PASS |
Tom Saunders
|
|
|
South Entrance Loops.
Underground to North Stairwell Phone #: ###-#### Inspection requested via web by Debby Pierce...
ok to cover
|
Electrical Rough-In | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | PASS |
Eric Story
|
|
|
Future feeder rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce u/g for future feeders ok cover
|
Electrical Rough-In | 2/27/2017 | 2/27/2017 | 2/27/2017 | P | PASS |
Rock A. Hudson
|
|
|
Underground branch rough-in for South Island and T1 branch conduits. Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PASS |
Rock A. Hudson
|
|
|
Underground branch conduits from Panel P ; Panel T1, between B8, B9, B10 to D8, D9, D10. Phone #: ###-#### Inspection requested via web by Debby Pierce Underground as noted rough in ok cover
|
Electrical Rough-In | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PASS |
Rock A. Hudson
|
|
|
West entrance traffic loops. Phone #: ###-#### Inspection requested via web by Debby Pierce 1st level area noted rough in ok cover
|
Electrical Rough-In | 2/20/2017 | 2/21/2017 | 2/21/2017 | P | PASS |
Rock A. Hudson
|
|
|
Contact George Morris ###-####. Feeder, and communications underground rough-in between grid lines 7 and 9 to column line C. Phone #: ###-#### Inspection requested via web by Debby Pierce Area as noted feeder underground rough in ok cover
|
Electrical Rough-In | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PASS |
Rock A. Hudson
|
|
|
underground for elec. room feeders ; communications. George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Feeder conduits from electrical room 30' towards main gear rough in ok cover
|
Electrical Rough-In | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | PASS |
Rock A. Hudson
|
|
|
George Morris is contact ###-####. West Entrance.... Phone #: ###-#### Inspection requested via web by Debby Pierce West entrance underground rough in ok cover
|
Electrical Rough-In | 2/13/2017 | 2/13/2017 | 2/13/2017 | P | PASS |
Tom Saunders
|
|
|
West Entrance Traffic Loops. George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce...
ok to cover
|
Electrical Rough-In | 2/9/2017 | 2/10/2017 | 2/10/2017 | A | PASS |
Rock A. Hudson
|
|
|
North ; South Stairwell....George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Area noted rough in ok cover
|
Electrical Rough-In | 2/6/2017 | 2/6/2017 | 2/6/2017 | P | PASS |
Rock A. Hudson
|
|
|
West Garage Entrance Phone #: ###-#### Inspection requested via web by Debby Pierce West entrance underground for pay stations rough in ok cover
|
Electrical Rough-In | 2/3/2017 | 2/3/2017 | 2/3/2017 | P | NR |
Rock A. Hudson
|
|
|
Rough In underground, George Morris is contact, ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Used for conference. Discussed if ENT could be encased in concrete and if fittings could be glued. NEC 362.10 states ENT is permitted in concrete and fittings shall be listed and installed as per manufactures instructions for that application. Future inspections if not ready for time requested will have re-inspection fee assessed.
|
Electrical Rough-In | 2/1/2017 | 2/2/2017 | 2/3/2017 | P | NR |
Rock A. Hudson
|
|
|
Underground. at 3pm if possible please. George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Underground did not get installed will recall when ready
|
Electrical Rough-In | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
James Ady
|
|
|
underground, George Morris is contact at ###-####. thank you Phone #: ###-#### Inspection requested via web by Debby Pierce 3/4in and 1in coduit running from E to W along North side of Site. Ok to cover
|
Electrical Rough-In | 1/11/2017 | 1/12/2017 | 1/12/2017 | A | PASS |
Rock A. Hudson
|
|
|
Underground Rough-In.... Mid Morning if at all possible. George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce West stair and elevator underground rough in ok cover
|
Electrical Rough-In | 1/4/2017 | 1/4/2017 | 1/4/2017 | P | PASS |
Rock A. Hudson
|
|
|
Underground, George Morris is contact at ###-####... Phone #: ###-#### Inspection requested via web by Debby Pierce Elevator and branch circuit underground conduits along column line C rough in ok cover
|
Electrical Rough-In | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | PASS |
Rock A. Hudson
|
|
|
UFER ground inspection Phone #: ###-#### Inspection requested via web by Debby Pierce General contractor would like us to check in at office each time. Told contractor OK to back fill travel areas only, will inspect all underground. Concrete encased electrode rough in ok cover
|