Final | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Rock A. Hudson
|
|
|
Final Inspection on the Gatehouse Contact Dan Hutchinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Final ok
|
Final | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PART |
Rock A. Hudson
|
|
|
Final Inspection for the Gatehouse Contact Dan Hutchinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Need complete upstairs lighting, underground for sign and pole lights deeper, receptacle with in 25' of HVAC units north side of building ground level, secure out conduits and disconnects on north side. TCO ok
|
Final | 5/30/2017 | 5/31/2017 | 5/31/2017 | P | FAIL |
Rock A. Hudson
|
|
|
Final Inspection for Gatehouse Contact Dan Hutchinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek BCC 4-05-32 Code violations not to be retained. While residing existing portion conduit supports removed. All MC shall be protected from physical damage and supported as per NEC. 210.8- GFCI protection for drinking fountain shall be installed at a readily accessible location. 210.63- Service receptacles shall be installed with in 25' of AC equpment. 210.64- Service receptacle shall be installed with in 50' of electric service. IBC- Emergency egress lighting providing 1 ft/candle of light shall be provided at exterior of each exit.
|
Electrical Rough-In | 5/24/2017 | 5/24/2017 | 5/24/2017 | A | PASS |
Mark Moncarr
|
|
|
Ceiling Inspection in the Gatehouse. Contact Dan Hutchinson ###-#### Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Ok cover ceiling in food prep area
|
Electrical Rough-In | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PASS |
Eric Story
|
|
|
Ceiling Inspection at the Gatehouse Contact Dan Hutchinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Suspended ceiling above reception desk and heater wall in riser room ok cover
|
Electrical Rough-In | 5/8/2017 | 5/9/2017 | 5/9/2017 | P | PASS |
Eric Story
|
|
|
Underground Inspection for in front of Gatehouse. Contact Dan Hutchinson Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek u/g for sign and gate ok cover
|
Electrical Rough-In | 4/5/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Rock A. Hudson
|
|
|
Rough-In Inspection for the gatehouse Contact Dan Hutchinson Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Walls and hardlids rough in ok cover
|
Electrical Rough-In | 3/16/2017 | 3/17/2017 | 3/17/2017 | A | PASS |
Rock A. Hudson
|
|
|
Underground Inspection on the Gatehouse. Contact Dan Hutchinson Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Underground must be under concrete due to 12" depth. Rough in ok cover
|
Permanent Service | 3/7/2017 | 3/7/2017 | 3/7/2017 | A | PASS |
Tom Saunders
|
|
|
Service Inspection Contact Dan Hutchinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek...
p/s u/g rec ok
|
Conference | 1/27/2017 | 1/27/2017 | 1/27/2017 | P | DONE |
Eric Story
|
|
|
Discussed service change and relocation of CT can, overcurrent device and main discconect will be on outsideof building due to unfused conductors ran inside building and not encased in concrete
|
Electrical Rough-In | 12/23/2016 | 12/23/2016 | 12/23/2016 | P | PASS |
Rock A. Hudson
|
|
|
Uffer ground inspection Contact Tom Betty Phone #: ###-#### Inspection requested via web by Cathy Duchek Concrete encased electode rough in ok cover
|