Final | 3/1/2017 | 3/2/2017 | 3/2/2017 | A | PASS |
Eric Story
|
|
|
Please call 30 minutes before you head over to make sure somebody will be there to get you inside. Thank you. David Phone #: ###-#### Inspection requested via web by Charmel Kubik Final for service change and bathroom addition ok
|
Final | 1/11/2017 | 1/12/2017 | 1/12/2017 | P | NR |
Mark Moncarr
|
|
|
Final for service change. Call before you head that way. Just to make sure there is someone there. Thank you. David. Phone #: ###-#### Inspection requested via web by Charmel Kubik Will final out permit for service when bathroom is ready for final
|
Electrical Rough-In | 1/10/2017 | 1/11/2017 | 1/11/2017 | A | DONE |
Tom Saunders
|
|
|
I will be moving a service down 30 inches, if I can get the ok to have Idaho power reconnect I will call in for another inspection on Thursday. Also I rewired a master bathroom. Phone #: ###-#### Inspection requested via web by Charmel Kubik
added p/s inspection
|
Rough-In Permanent Service | 1/11/2017 | 1/11/2017 | 1/11/2017 | A | PASS |
Tom Saunders
|
|
|
I will be moving a service down 30 inches, if I can get the ok to have Idaho power reconnect I will call in for another inspection on Thursday. Also I rewired a master bathroom. Phone #: ###-#### Inspection requested via web by Charmel Kubik
rough in new master bath ok...panel moved for clearance p/s o/h rec ok
|