Information based on query as of Monday, July 8, 2024.
Permit Information
Permit NumberELE17-00052
StatusFinaled
Name TASKER ELECTRICAL CONSTRUCTION INC
Site Address 280 S CAPITOL BLVD
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration: update building lighting, update the electrical for fire alarm system, install switches, outlets and wire for upgrades.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final4/17/20174/18/20174/18/2017APASS
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Stacie Tasker
Final ok
Final4/14/20174/17/20174/17/2017AFAIL
DetailsRock A. Hudson
Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
210.8- Drinking fountain shall have GFCI protection that is readily accessible.
210.70- Outdoor egress lighring not installed as per print.
Electrical Rough-In3/23/20173/24/20173/24/2017PPASS
DetailsRock A. Hudson
We need a ceiling inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
All ceilings rough in ok cover
Electrical Rough-In3/22/20173/23/20173/23/2017APASS
DetailsRock A. Hudson
We need a ceiling inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
except kitchenette and storage rms. 1st floor grid rough in ok cover
Electrical Rough-In2/21/20172/22/20172/22/2017PPASS
DetailsRock A. Hudson
We need a ceiling cover on 2nd floor. Gary is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker
No new walls on 2nd floor, new offices shown on print were not built.
2nd floor grid rough in ok cover.
Electrical Rough-In1/16/20171/17/20171/17/2017APASS
DetailsEric Story
We need a wall cover inspection. Gary is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Walls on first floor only ok cover