Final | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PASS |
Mark Moncarr
|
|
|
Approved plans onsite. Everything located on exterior, howeve,r homeowner will have to open gate and wrangle dogs, please call Matt Cooper before arrival ###-####. Ryan King can answer questions, ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Ryan King Ok final
|
Electrical Rough-In | 3/10/2017 | 3/10/2017 | 3/10/2017 | P | PASS |
Mark Moncarr
|
|
|
Trench and conduit inspection, we''ll have the trench open and conduit placed early afternoon today, please coordinate w/ Ed Harrington ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Ryan King Trench ok cover
|
Electrical Rough-In | 2/9/2017 | 2/10/2017 | 2/10/2017 | A | PASS |
Eric Story
|
|
|
Listing Inspection, Approved plans and equipment onsite. Phone #: ###-#### Inspection requested via web by Ryan King Verfied listing of solar array panels and inverters and location of panels
|