Final | 4/12/2017 | 4/13/2017 | 4/13/2017 | A | PASS |
Rock A. Hudson
|
|
|
Call when about to site and I will come over and meet you Phone #: ###-#### Inspection requested via web by steve ragan Final ok
|
Final | 4/12/2017 | 4/13/2017 | 4/12/2017 | A | CANC |
Rock A. Hudson
|
|
|
Phone #: ###-#### >> Inspection requested via web by steve ragan Inspection cancelled from web by: steve ragan
|
Electrical Rough-In | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Rock A. Hudson
|
|
|
2nd phase of project. Roughed in electrical in new wall of conference room Phone #: ###-#### Inspection requested via web by steve ragan Phase 2 walls rough in ok cover
|
Electrical Rough-In | 2/9/2017 | 2/10/2017 | 2/10/2017 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by steve ragan Phase 2 will be 2 conference rooms and 1 office. Today phase 1, 3 offices, break and work area wall rough in ok cover
|