Final | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | PASS |
Rock A. Hudson
|
|
|
Added 3 new LED EM lights on columns, 1st floor, in corridor line of egress. New MC cable was run to the closest lighting junction boxes that serves that area. New wires were pulled into existing conduits, to get constant hot to EM lights. Phone #: ###-#### Inspection requested via web by Kurt Carlson Final ok
|
Electrical Rough-In | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | PASS |
Rock A. Hudson
|
|
|
Added 3 new LED EM lights on columns, 1st floor, in corridor line of egress. New MC cable was run to the closest lighting junction boxes that serves that area. New wires were pulled into existing conduits, to get constant hot to EM lights. Phone #: ###-#### Inspection requested via web by Kurt Carlson Rough in ok
|