Permit Information
Permit NumberELE17-00392
StatusFinaled
Name QUALITY ELECTRIC INC
Site Address 8000 S FEDERAL WAY
Project NameMicron B51 R & D Facility
Customer Number16082
ePlanReviewNo
Description
Alteration: Work for finishing of shell and core, Micron R&D Building 51. Reference BLD16-03440. Work is not included in electrical permit ELE16-04054.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/18/201810/19/201810/19/2018APASS
DetailsJames Ady
Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell Core and shell only Final ok
Final11/7/201711/8/201711/8/2017APART
DetailsJames Ady
This is a partial final. Contact is Rene Ramakers. Phone #: ###-#### Inspection requested via web by Scott Campbell tool set only temp ok
Final8/9/20178/11/20178/11/2017APART
DetailsJames Ady
This is a partial final / occupancy inspection. Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell Partial final Tool set only ok
Electrical Rough-In7/26/20177/26/20177/26/2017PPASS
DetailsJames Ady
Cover inspection. Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell high volt panel to low volt trans and D board ok
Final6/29/20176/30/20176/30/2017APART
DetailsJames Ady
This is a partial final again for occupancy. Contact is Rene Ramakers. Phone #: ###-#### Inspection requested via web by Scott Campbell Partial only tool set only
Final6/26/20176/29/20176/29/2017PPART
DetailsJames Ady
This is a partial final per discussion between James Ady and Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell Tool Set only. Temp only
Electrical Rough-In6/16/20176/20/20176/20/2017APASS
DetailsJames Ady
Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell walk through on building 51. Discussed areas needing TCO
Electrical Rough-In6/12/20176/12/20176/12/2017PCANC
DetailsJames Ady
Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell needed conference
Conference6/12/20176/12/20176/12/2017PDONE
DetailsJames Ady
Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell Talked about TCO requirements. Need Life safety items taken care of.
Electrical Rough-In5/4/20175/4/20175/4/2017PPASS
DetailsJames Ady
Contact is Rene Ramakers Phone #: ###-#### Inspection requested via web by Scott Campbell Stairways only ok to cover. Interstitial walk through, Check Building steel bond for Transformer
Conference3/28/20173/31/20173/31/2017ADONE
DetailsJames Ady
Phone #: ###-#### Talked about working clearances above "D" board. Any "D" board with water lines above shall have sheilds installed
Electrical Rough-In3/24/20173/24/20173/24/2017PPASS
DetailsJames Ady
Rene Phone #: ###-#### Sub fab Switch gear wall
Electrical Rough-In2/22/20172/23/20172/23/2017APASS
DetailsJames Ady
Contact is Rene Ramakers. Cover inspection Phone #: ###-#### Inspection requested via web by Scott Campbell underground and wall cover as marked on City set ok to cover