Final | 6/5/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Tom Saunders
|
|
|
We are requesting a final inspection on this project, our onsite contact is Luke, ###-#### Phone #: ###-#### Inspection requested via web by Clint Tate....
heaters installed, panel labelled...job complete ok to final
|
Final | 5/30/2017 | 5/30/2017 | 5/30/2017 | A | PART |
Tom Saunders
|
|
|
temp occupency...clint tate....
2 offices complete, breakroom extension complete....left for final is bathroom heaters and labelling of panel circuits
|
Temporary Service | 5/26/2017 | 5/30/2017 | 5/30/2017 | A | CANC |
Tom Saunders
|
|
|
We are requesting a inspection for temp. Occupancy for Tuesday May 30th in the morning. Our contact is Larry @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate...wrong inspection
|
Electrical Rough-In | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Tom Saunders
|
|
|
we are asking for an above ceiling inspection for today. please call if necessary, POC is larry ###-#### Phone #: ###-#### Inspection requested via web by Clint Tate...
ok to cover
|
Electrical Rough-In | 4/19/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Tom Saunders
|
|
|
We are requesting a rough-in inspection for tomorrow afternoon. Our contact is Luke @###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate...
rough ok to cover...bathroom, shower area, breakroom, 3 new offices
|