Final | 5/8/2017 | 5/8/2017 | 5/8/2017 | P | PASS |
James Ady
|
|
|
We will be completing second part of the rough in, the sub panel on the back of the home. IPCO will be shutting power off and transferring to the new service, We will be ready for rough in and final inspection around 2 ish today. Phone #: ###-#### Inspection requested via web by Kurt Carlson Final ok
|
Permanent Service | 4/24/2017 | 4/24/2017 | 4/24/2017 | A | PASS |
James Ady
|
|
|
Need new 200 amp meter/ main service inspected. Located on side of home. 2 ground rods were driven, new #4 copper was installed and connected within 5'' entry of metal water line. More work to follow during power transfer and shut down day. Call me, Kurt ###-#### Phone #: ###-#### Inspection requested via web by Kurt Carlson p/s o/h rec ok
|