Final | 5/5/2017 | 5/8/2017 | 5/8/2017 | A | PASS |
Tom Saunders
|
|
|
Call an hour beforehand if you need the electrician on site. Phone #: ###-#### Inspection requested via web by Christian Kilpatrick...
ok to final
|
Electrical Rough-In | 5/2/2017 | 5/3/2017 | 5/3/2017 | P | PASS |
Mark Moncarr
|
|
|
This is for a power turn on after a solar panel change out. Please call beforehand to see if we are ready for this to be inspected.
Thank you Phone #: ###-#### Inspection requested via web by Christian Kilpatrick p/s u/g n ok
|