Final | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
Rock A. Hudson
|
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
Permanent Service | 6/19/2017 | 6/19/2017 | 6/19/2017 | P | PASS |
Rock A. Hudson
|
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden p/s u/g rec ok
|
Permanent Service | 6/6/2017 | 6/8/2017 | 6/8/2017 | A | FAIL |
Rock A. Hudson
|
|
|
Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden 110.9- Equipment intended to interupt current at fault levels shall have an interupting rating at nominal circuit voltage at least equal to the current available at the line terminals of the equipment. 16,448 available and 10k rated equipment installed.
|