Final | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PASS |
James Ady
|
|
|
Swimming pool electrical Phone #: ###-#### Inspection requested via web by Lars Johnson Pool only Final ok
|
Electrical Rough-In | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | PASS |
Daryl DeGrange
|
|
|
Swimming pool light potting (4) Phone #: ###-#### Inspection requested via web by Lars Johnson Rough-in ok
|
Electrical Rough-In | 7/6/2017 | 7/10/2017 | 7/10/2017 | P | PASS |
Rock A. Hudson
|
|
|
EQ bonding Phone #: ###-#### Inspection requested via web by Lars Johnson EQ on both, rail cups and base at east end bonding rough in ok cover
|
Electrical Rough-In | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
James Ady
|
|
|
Remaining undrground from pools to equipment room Phone #: ###-#### Inspection requested via web by Lars Johnson underground to pools only ok to cover
|
Electrical Rough-In | 5/30/2017 | 5/31/2017 | 5/31/2017 | P | PASS |
James Ady
|
|
|
Partial ug and bonding: Ug for (4) pool lights ; (3) kiddie pool lights Bonding for (8) EQ corners, (2) steel/equipment, (4) pool lights, (2) handrails, (1) handicap lift Phone #: ###-#### Inspection requested via web by Lars Johnson :Lighting, corners,Handrails bonds only ok to cover
|
Electrical Rough-In | 5/9/2017 | 5/10/2017 | 5/10/2017 | A | PASS |
James Ady
|
|
|
Partial underground in pool equipment room Phone #: ###-#### Inspection requested via web by Lars Johnson Underground stubs from pool Mechanical room only ok to cover
|