Permit Information
Permit NumberELE17-01458
StatusFinaled
Name MOUNTAIN POWER ELECT
Site Address 12142 W JOPLIN RD
Project Name 
Customer Number17-005
ePlanReviewNo
Description
New: Electrical wiring - Building service, light Fixtures and fire blast equipment connections
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final4/11/20184/11/20184/11/2018PPASS
DetailsTom Saunders
Inspection requested via web by Jeremy Cloud..building complete...ok to final...propane tank associated with building has pneumatic emergency shutoff...all associated piping inspected by others and no electrical work done under electrical permit
Final3/29/20183/30/20183/30/2018PCANC
DetailsTom Saunders
Phone #: ###-#### Inspection requested via web by Jeremy Cloud...not ready
Permanent Service1/25/20181/25/20181/25/2018PPASS
DetailsTom Saunders
Inspect burn tower service to energize Phone #: ###-#### Inspection requested via web by Jeremy Cloud...p/s u/g new ok
Electrical Rough-In1/25/20181/25/20181/25/2018PPASS
DetailsTom Saunders
Inspect burn tower service to energize Phone #: ###-#### Inspection requested via web by Jeremy Cloud....floor 3, floor 5, and roof top slab for concrete pours verified ok...extensions from each floor
Electrical Rough-In10/17/201710/18/201710/18/2017APASS
DetailsTom Saunders
Inspect 4th floor slab rough in for concrete pour Phone #: ###-#### Inspection requested via web by Jeremy Cloud...ok to pour
Electrical Rough-In8/24/20178/25/20178/25/2017PPASS
DetailsTom Saunders
Need inspection of 2nd floor deck rough in on burn tower. Phone #: ###-#### Inspection requested via web by Jeremy Cloud...

ok to cover
Electrical Rough-In6/6/20176/7/20176/7/2017PPASS
DetailsTom Saunders
Please inspect Stairwell Walls. Call Corey at ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Kevin Perez...

ok to cover...elevator walls...marked on plans...future inspections will be marked on plans
Electrical Rough-In5/16/20175/17/20175/17/2017APASS
DetailsTom Saunders
Need UFER ground inspected for concrete pour Phone #: ###-#### Inspection requested via web by Jeremy Cloud...

verified ok to cover