Final | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Tom Saunders
|
|
|
Please call Lynn at ###-####. Phone #: ###-#### Inspection requested via web by Lynn Proctor...
job complete...ok to final
|
Electrical Rough-In | 6/29/2017 | 6/30/2017 | 6/30/2017 | P | PASS |
Tom Saunders
|
|
|
Ceiling Grid Inspection Needed. Please call Lynn prior to inspection at ###-####. Phone #: ###-#### Inspection requested via web by Lynn Proctor...
ok to cover
|
Electrical Rough-In | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PASS |
Tom Saunders
|
|
|
Please call Lynn at ###-#### for directions on what we need inspected. Phone #: ###-#### Inspection requested via web by Lynn Proctor....
new walls ok to cover, above new panels ok to cover
|
Electrical Rough-In | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PASS |
Tom Saunders
|
|
|
Please inspect the floor boxes so that we can have the concrete slab poured back. Phone #: ###-#### Inspection requested via web by Lynn Proctor...
ok to cover...multiple floor boxes in a row
|