Final | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud...job complete...ok to final...no card to sign
|
Final | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PART |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud...partial final for temp occupency...site lighting, gate power, charging stations needed completed, and front desk outlet
|
Electrical Rough-In | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | PASS |
Tom Saunders
|
|
|
Inspect IT room ceiling for cover Phone #: ###-#### Inspection requested via web by Jeremy Cloud...ok to cover...grid complete
|
Electrical Rough-In | 1/11/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Mark Moncarr
|
|
|
Inspect overhead rough-in for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Ok cover ceiling throughout except IT closet.
|
Permanent Service | 12/15/2017 | 12/18/2017 | 12/18/2017 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Training and safety building. 9,500 Available fault current. p/s u/g n ok
|
Electrical Rough-In | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Tom Saunders
|
|
|
Inspect all walls for cover Phone #: ###-#### Inspection requested via web by Jeremy Cloud....wall cover admin building..ok to cover
|
Electrical Rough-In | 5/26/2017 | 5/26/2017 | 5/26/2017 | A | PASS |
Tom Saunders
|
|
|
Ufer inspection for concrete pour Phone #: ###-#### Inspection requested via web by Jeremy Cloud...
varified...ok to cover
|