Final | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Mark Moncarr
|
|
|
Please contact Lance Barg Phone #: ###-#### Inspection requested via web by David Ok final.
|
Electrical Rough-In | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PASS |
Mark Moncarr
|
|
|
Rough-in inspection for the ceiling Phone #: ###-#### Inspection requested via web by David Feller Ok cover ceiling throughout. 1 MC needed lifted off T grid, told contractor and said he would get it fixed.
|
Electrical Rough-In | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | PASS |
Mark Moncarr
|
|
|
Please contact Lance Bard at # noted above. Need a Partial Ceiling Rough-In inspection no later than 1:30 p.m. Thanks... David Phone #: ###-#### Inspection requested via web by David Feller Ok cover perimeter ONLY in all offices and meeting rooms.
|
Electrical Rough-In | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | PASS |
Mark Moncarr
|
|
|
hard lid rough in inspection in ceiling - tomorrow am Phone #: ###-#### Inspection requested via web by David Feller Ok cover lid in conference rm, waiting rm and ceiling by N stairwell.
|
Electrical Rough-In | 6/19/2017 | 6/20/2017 | 6/20/2017 | A | PASS |
Rock A. Hudson
|
|
|
Wall rough in.
For questions, please speak with Scott Thomas (number provided above)
Thanks... Phone #: ###-#### Inspection requested via web by David Feller Fire alarm boxes located above future hardlid are to be removed and new low volt system being installed. Wall rough in ok cover
|