Final | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
James Ady
|
|
|
Final Inspection for AceCo Contact Damonn Barr Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Final ok
|
Permanent Service | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
James Ady
|
|
|
Contact Damonn Barr Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek p/s u/g n ok 2 meters
|
Conference | 7/7/2017 | 7/7/2017 | 7/7/2017 | P | DONE |
James Ady
|
|
|
Contact Damonn Barr Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Discussed grounding and use of Exhisting bond. Exhisting electrode system is big enough to handle added service. Discussed need to relocate Meter/Main to left side of gear as Idaho power clearences to gas meter would not be met.
|