Final | 7/27/2018 | 7/30/2018 | 7/30/2018 | P | PASS |
Tom Saunders
|
|
|
Please Call Mike Phone #: ###-#### Inspection requested via web by Kevin Perez...ok to final for occupency of all rooms...2nd permit will need pulled for equipment in engineering rm
|
Final | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PART |
Tom Saunders
|
|
|
final off all classrooms, roof top units, exterior, minus engineering room...temp occupency given to all areas excluding engineering room-waiting on equipment and circuit wiring
|
Final | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Tom Saunders
|
|
|
Please call Mike. Phone #: ###-#### Inspection requested via web by Kevin Perez..marked areas ceiling grids and classrooms...rm 116 1 GFCI needed, exterior outlets WR GFCI, hall 119 GFCI protection for vending machines, HVAC disconnects circuit labelling and service outlet needed
|
Electrical Rough-In | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PART |
Rock A. Hudson
|
|
|
Please Call Mike. Phone #: ###-#### Inspection requested via web by Kevin Perez Rooms marked on print not ready, door power at exits and 115, 116, 124, 126 Class rooms and corridor clouds as noted on contractor print, grid rough in ok cover
|
Permanent Service | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud...p/s u/g new ok
|
Conference | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Tom Saunders
|
|
|
discussed outlets above ceiling grid discussed clearances for disconnects on roof units with gas piping in front of...ok'd by Tom discussed requirements for service inspection
|
Electrical Rough-In | 5/9/2018 | 5/10/2018 | 5/10/2018 | A | PASS |
Tom Saunders
|
|
|
Please Call Mike McCarrel Phone #: ###-#### Inspection requested via web by Kevin Perez...hard lid bathrooms and entry hall ok to cover
|
Electrical Rough-In | 4/18/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Tom Saunders
|
|
|
Please Call Mike McCarrel Phone #: ###-#### Inspection requested via web by Kevin Perez....electrical rm, tech/engineering rm walls...wall inspections complete..ok to cover
|
Electrical Rough-In | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | PASS |
Tom Saunders
|
|
|
Please call Mike McCarrel Phone #: ###-#### Inspection requested via web by Kevin Perez...wall cover...marked on plans ok to cover
|
Electrical Rough-In | 3/16/2018 | 3/19/2018 | 3/19/2018 | A | PASS |
Tom Saunders
|
|
|
Please Call Mike Phone #: ###-#### Inspection requested via web by Kevin Perez...wall cover ok as marked on plans
|
Electrical Rough-In | 2/15/2018 | 2/16/2018 | 2/16/2018 | A | PASS |
Tom Saunders
|
|
|
Please call Mike.
This is for a partial wall rough-in. Phone #: ###-#### Inspection requested via web by Kevin Perez...wall cover ok walls as marked on plans
|
Electrical Rough-In | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PASS |
Tom Saunders
|
|
|
Please Call Mike.
This is for a underground rough in inspection. Phone #: ###-#### Inspection requested via web by Kevin Perez...ok to cover west side floor boxes and east side underground feeds
|
Electrical Rough-In | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | PASS |
Tom Saunders
|
|
|
Please Call Mike.
This is for a underground rough-in inspection. Phone #: ###-#### Inspection requested via web by Kevin Perez..underground feeds for east side of building...ok to cover
|
Electrical Rough-In | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PASS |
Tom Saunders
|
|
|
Please call Mike This inspection is for the under ground ufer Phone #: ###-#### Inspection requested via web by Kevin Perez...
ok to cover
|
Electrical Rough-In | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PASS |
Tom Saunders
|
|
|
please call Mike Phone #: ###-#### Inspection requested via web by Kevin Perez...
underground sleeves to main service ok to cover
|
Electrical Rough-In | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PASS |
Mark Moncarr
|
|
|
This is for the under ground you have already looked at. if you have any questions please call our guy onsite Mike. Phone #: ###-#### Inspection requested via web by Kevin Perez Ok cover. Looked at on 9/1/17
|
Temporary Service | 8/29/2017 | 9/1/2017 | 9/1/2017 | P | PASS |
Mark Moncarr
|
|
|
Please Call Mike Phone #: ###-#### Inspection requested via web by Kevin Perez t/s u/g n ok
|
Electrical Rough-In | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Eric Story
|
|
|
Please Cal Mike Phone #: ###-#### Inspection requested via web by Kevin Perez 4-4" secondary conduits and 2" temp conduit ok to cover
|
Electrical Rough-In | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | PASS |
Eric Story
|
|
|
Please Call Jason Park
This is for a underground inspection. Phone #: ###-#### Inspection requested via web by Kevin Perez Conduit from school to job trailer on east side and in front of school ok cover
|