Final | 6/14/2018 | 6/19/2018 | 6/18/2018 | A | PASS |
Mark Moncarr
|
|
|
approved plans on site. Listing inspection has been done. Phone #: ###-#### Inspection requested via web by Ryan King Ok final. Looked at job on 6/18/18 a long with RI. Installer was on site to pull off panel to verify UL listing.
|
Electrical Rough-In | 6/14/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Mark Moncarr
|
|
|
Listing inspection for solar equipment.
The panel crew will get there mid afternoon. They will be coming from another listing inspection, so we are subject to inspector availability. Please call ahead to make sure you don''t beat us there. Phone #: ###-#### Inspection requested via web by Ryan King Ok cover. All items UL listed.
|
Final | 6/13/2018 | 6/15/2018 | 6/14/2018 | P | CANC |
Mark Moncarr
|
|
|
Approved plans on site. Call ahead to customer for garage access. Call Ryan King for any questions Thanks again Phone #: ###-#### >> Inspection requested via web by Ryan King Inspection cancelled from web by: Ryan King
|