Final | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Card signed..... Final ok
|
Final | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PART |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud 110.16- Arc flash labels shall be installed. 314.25- Covers shall be installed on all boxes. 1 fire riser room, one 3 gang one 4 gang level 1 electrical rm, and up bath switch. 110.3- Complete up stairs furniture installation.. Signed TCO.
|
Final | 8/2/2018 | 8/3/2018 | 8/3/2018 | P | CANC |
Eric Story
|
|
|
Phone #: ###-#### >> Inspection requested via web by Jeremy Cloud Inspection cancelled from web by: Jeremy Cloud
|
Electrical Rough-In | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Eric Story
|
|
|
Inspect 2nd floor ceiling for cover Phone #: ###-#### Inspection requested via web by Jeremy Cloud 2nd floor ceilings ok to cover
|
Electrical Rough-In | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Eric Story
|
|
|
Inspect first floor grid ceilings for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud 1st floor suspended ceilings ok to cover
|
Electrical Rough-In | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
Eric Story
|
|
|
Inspect underground site piping on north side of building for cover Phone #: ###-#### Inspection requested via web by Jeremy Cloud u/g ok to cover
|
Permanent Service | 6/29/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Eric Story
|
|
|
Inspect new service to energize Phone #: ###-#### Inspection requested via web by Jeremy Cloud Highest value given is 20818 and frame of breaker is 65K rated p/s u/g n ok
|
Electrical Rough-In | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Eric Story
|
|
|
Inspect drive through canopy and underground piping on south side of building for cover Phone #: ###-#### Inspection requested via web by Jeremy Cloud Canopy and u/g ok to cover
|
Electrical Rough-In | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | CANC |
Eric Story
|
|
|
Inspect drive through canopy for cover Phone #: ###-#### >> Inspection requested via web by Jeremy Cloud Inspection cancelled from web by: Jeremy Cloud
|
Electrical Rough-In | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Rock A. Hudson
|
|
|
Need to inspect hard lid above NW stairwell for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Area noted rough in ok cover
|
Electrical Rough-In | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Eric Story
|
|
|
Mark Phone #: ###-#### 2nd floor soffits and bath walls ok to cover
|
Electrical Rough-In | 6/7/2018 | 6/8/2018 | 6/8/2018 | A | PART |
Eric Story
|
|
|
Mark Phone #: ###-#### 2nd floor raised floor and west offices as well as south offices walls only ok to cover
|
Electrical Rough-In | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Eric Story
|
|
|
Mark Phone #: ###-#### N stair soffit on 1st floor and 2nd floor shaft wall and 2nd floor east stair ceiling ok to cover
|
Electrical Rough-In | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Eric Story
|
|
|
1st fl ceiling - Mark Phone #: ###-#### 1st floor hard lids and soffit ok to cover
|
Electrical Rough-In | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Eric Story
|
|
|
2nd fl walls - Mark Phone #: ###-#### 2nd floor walls only ok to cover
|
Electrical Rough-In | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Eric Story
|
|
|
Mark Phone #: ###-#### Entry walls and drive thru walls ok to cover
|
Electrical Rough-In | 4/2/2018 | 4/3/2018 | 4/3/2018 | P | PASS |
Eric Story
|
|
|
Mark Phone #: ###-#### Walls on 1st floor and 2nd floor parapet receptacles ok to cover
|
Electrical Rough-In | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Eric Story
|
|
|
Treon Phone #: ###-#### U/G for sign ok to cover(only at the concreted block at this time)
|
Electrical Rough-In | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Eric Story
|
|
|
Underground - Treon Phone #: ###-#### U/G for drive thru area ok to cover
|
Electrical Rough-In | 12/29/2017 | 12/29/2017 | 12/29/2017 | P | PASS |
Eric Story
|
|
|
underground // treon Phone #: ###-#### u/g for secondary to biuildings ok to cover
|
Electrical Rough-In | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | PASS |
Eric Story
|
|
|
underground- Treon Phone #: ###-#### Remaining u/g in electrical room ok to cover
|
Electrical Rough-In | 12/14/2017 | 12/15/2017 | 12/15/2017 | P | PASS |
Eric Story
|
|
|
UG // Jake Phone #: ###-#### Phase 1 underground ok to cover
|
Electrical Rough-In | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Eric Story
|
|
|
Please Call Jason Parke
This is for a Ufer Ground inspection. Phone #: ###-#### Inspection requested via web by Kevin Perez Concrete encased electrode ok to cover
|
Electrical Rough-In | 10/20/2017 | 10/20/2017 | 10/20/2017 | A | CANC |
Eric Story
|
|
|
Please Call Jason Parke
This is for a Ufer Ground inspection Phone #: ###-#### >> Inspection requested via web by Kevin Perez Inspection cancelled from web by: Kevin Perez
|
Electrical Rough-In | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PASS |
Daryl DeGrange
|
|
|
Please call Jason P.
This is for a electrical underground inspection. Phone #: ###-#### Inspection requested via web by Kevin Perez Rough-in ok cover raceways under footings
|