Final | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Mark Moncarr
|
|
|
Call Gil, the General Contractor with Falash ; Ross when in route if possible @ ###-####.
Or, Steve with Patriot Electric at ###-####. Phone #: ###-#### Inspection requested via web by Steve McCloy Ok final.
|
Electrical Rough-In | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
James Ady
|
|
|
Call Gil; the General Contractor with Falash ; Ross at ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Steve McCloy ceiling only ok to cover
|
Electrical Rough-In | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Mark Moncarr
|
|
|
Call Steve when in route if possible. Phone #: ###-#### Inspection requested via web by Steve McCloy Ok cover. Multiple locations on 2nd floor. No room numbers to list. Will need Steve on site for final to cover all areas.
|