Final | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Eric Story
|
|
|
Kenny is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker final ok
|
Electrical Rough-In | 5/25/2018 | 5/25/2018 | 5/25/2018 | P | PASS |
Tom Saunders
|
|
|
Please call Kenny 30 minutes prior to arrival. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker...ok to pour concrete and cover heat wire...8 circuits 40 A ea
|
Electrical Rough-In | 11/29/2017 | 11/30/2017 | 11/30/2017 | A | PASS |
Tom Saunders
|
|
|
We need an underground inspection, Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...south end pipes ok to cover
|
Electrical Rough-In | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Tom Saunders
|
|
|
We need a partial underground for North half. Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker...ok to cover...underground north side, reader board, landscape, and pole lights
|
Electrical Rough-In | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection, please! Tobias is the site contact Phone #: ###-#### Inspection requested via web by Stacie Tasker Additional 12" of fill will be brought in before final cover. South trenches with 1 more will be done in future and covered area underground rough in ok cover
|