Permit Information
Permit NumberELE17-03734
StatusFinaled
Name ENTERPRISE ELECTRIC
Site Address 222 N 8TH ST
Project NameDiablo & Sons Mezcaleria
Customer Number 
ePlanReviewNo
Description
Alteration: Demo existing electrical in Basement and Install new wiring, LED fixtures, Emergency Lighting, Panelboards, feeders, branch wiring, devices, and equipment connections.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  10/18/2018 DONE
project finished out by other Electrical Contractor under ELE18-03898
Conference9/21/20189/21/20189/21/2018PPASS
DetailsRock A. Hudson
Spoke with general foreman on site. All work performed after 9-14-18 must be done and permitted by a licenced contractor due to original contractor no longer in business.
Final9/13/20189/14/20189/14/2018AFAIL
DetailsRock A. Hudson
Requesting partial final for TCO. Contact is Kory Peterson Phone #: ###-#### Inspection requested via web by Clint Tate
Contact informed me of Quality Electric are no longer open for business. A new contractor has taken over job. Areas are cluttered with equipment and areas are taped off so must reschedule when access available to all areas. Unable to locate general foreman or new electrical contractor.
Electrical Rough-In9/6/20189/7/20189/7/2018APASS
DetailsMark Moncarr
Requesting rough inspection on the back bar and above t-grid ceilings Phone #: ###-#### Inspection requested via web by Clint Tate Ok cover ceiling in kitch area. Back bar ok cover. 1 4sq needs mounted after beer taps installed. Box has grd pigtail.
Electrical Rough-In7/11/20187/12/20187/12/2018APASS
DetailsRock A. Hudson
Requesting re-inspection of the panel wall where the plumbing lines have been relocated per the field meeting Phone #: ###-#### Inspection requested via web by Clint Tate
Panel wall rough in ok cover
Conference7/2/20187/3/20187/3/2018PFAIL
DetailsRock A. Hudson
Requesting an inspection consultation to review the panel wall that failed inspection previously. Specifically requesting Daryl to review any possible solutions to this issue. Phone #: ###-#### Inspection requested via web by Clint Tate
As noted dedicated electrical space width and depth of panel board shall be clear for future expansion as per 110.26(E)(1)(a). As per conversation with Daryl DeGrange if only way to reconnect to pipes passing thru floor is in original area, only the amount permitted would be a 90 degree connector to leave dedicated electrical space.
Conference6/27/20186/28/20186/28/2018PNH
DetailsRock A. Hudson
Requesting a consultation with Daryl specifically to review the panel wall which failed inspection on June 21st. The General Contractor will be scheduling the plumbing inspector as well to review all possible solutions. Please provide 1/2 hour notice before arriving to site to ensure all parties are present. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Called contact and explained Chief Electrical Inspector is off thru end of week and should return July 2. I told I had a meeting with Chief about correction and he agreed shall be code compliant. If would still like to meet will have to wait until Monday when he returns.
Electrical Rough-In6/20/20186/21/20186/21/2018APASS
DetailsRock A. Hudson
Requesting partial rough for bar area Phone #: ###-#### Inspection requested via web by Clint Tate
Bar 1/2 wall only rough in ok cover
Electrical Rough-In6/21/20186/21/20186/21/2018PFAIL
DetailsRock A. Hudson
Requesting partial rough for bar area Phone #: ###-#### Inspection requested via web by Clint Tate
Panel wall. 110.26(E)(1)1a- Space equal to width and depth of equipment shall be dedicated electrical space and shall have no other systems in this space. below panels
Electrical Rough-In6/4/20186/5/20186/5/2018APASS
DetailsRock A. Hudson
Contact name: Luke Hardy Phone #: ###-#### Inspection requested via web by Clint Tate
Level 1 vestibules and level 2 chase to roof rough in ok cover
Electrical Rough-In5/10/20185/11/20185/11/2018PPASS
DetailsRock A. Hudson
Requesting rough-in inspection for the new restaurant. Contact is Luke Hardy ###-####. Phone #: ###-#### Inspection requested via web by Clint Tate
Wall rough in ok cover
Electrical Rough-In4/3/20184/3/20184/3/2018PPASS
DetailsRock A. Hudson
Discussed show window receptacle requirements. Windows above garage style doors used as windows shall be concidered windows that could be used to advertise and shall have minimum required receptacles installed.
NEC definitions. Show Window. Any window, including windows above doors, used or designed to be used for the display of goods or advertising material, whether it is fully or partly enclosed or entirely open at the rear and whether or not it has a platform raised higher than the street floor level. (CMP-2)
Warm and dry storage rooms only
walls and hardlids rough in ok cover.
Conference2/28/20182/28/20182/28/2018PDONE
DetailsRock A. Hudson
Discussed stairway to alley lighting and sump room.
On stairway to alley the lighting has been removed for stairway and shall be reinstalled asap as this path is being used daily.
Sump pump room will be used as a spray down room. A pressure washer will be present in room. Room shall be concidered a wet location.
Electrical Rough-In2/28/20182/28/20182/28/2018PPASS
DetailsRock A. Hudson
We are requesting a wall rough-in in the basement area for this afternoon. Our contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Prep kitchen #2 to right of door walls and hard lid rough in ok cover
Electrical Rough-In12/13/201712/14/201712/14/2017APART
DetailsRock A. Hudson
This inspection is for temporary occupancy of the partial prep room which failed the last inspection due to the BLD permit still under review. Our understanding is this would be resolved between the Architect and City today. Site Contact: Luke Hardy, ###-####. Phone #: ###-#### Inspection requested via web by Larry Looney
No rough in needed. Created to note for ok occupy prep room A.
Rough-In Permanent Service12/12/201712/12/201712/12/2017PPASS
DetailsRock A. Hudson
We are hoping for a Temporary Occupancy inspection for this afternoon. Our contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Unable to give temp occupancy due to BLD has been resubmitted for plan mod and is under review.
210.8(B)- All receptacles located in kitchen areas shall have GFCI protection.
Walls in worm room rough in ok cover
Electrical Rough-In11/30/201711/30/201711/30/2017PPASS
DetailsRock A. Hudson
We are requesting a rough-in inspection walls and ceiling for this afternoon. Our contact is Luke ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Prep room A homerun cove only rough in ok cover
Electrical Rough-In11/27/201711/28/201711/28/2017PPART
DetailsJames Ady
We are requesting a partial rough-in inspection for the basement walls. Our contact is Luke at ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate Prep room A walls and lid minus home run cove on East side of room
Electrical Rough-In11/3/201711/3/201711/3/2017PPASS
DetailsRock A. Hudson
Underfloor conduits rough in ok cover