ELE-Aging Inspection | 5/18/2020 | 5/18/2020 | 5/18/2020 | | DONE |
Daryl DeGrange
|
|
|
Spoke with contractor, David agreed to schedule an final
|
ELE-Aging Inspection | 2/17/2020 | 2/17/2020 | 2/18/2020 | | DONE |
Mark Moncarr
|
|
|
Spoke with David on 2/18. He thought building was finaled. He is going to go by business and try to schedule a final.
|
ELE-Aging Inspection | 11/18/2019 | 11/18/2019 | 11/20/2019 | | DONE |
Daryl DeGrange
|
|
|
Spoke with contractor, discussed required final inspection.
|
Rough-In Permanent Service | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Eric Story
|
|
|
service inspection after fire- UNIT B-105 Phone #: ###-#### Inspection requested via web by David Nelson ok to cover existing wiring p/s u/g rec ok
|