Final | 7/27/2018 | 7/27/2018 | 7/27/2018 | P | PASS |
Rock A. Hudson
|
|
|
George Morris is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Final ok
|
Final | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PART |
Rock A. Hudson
|
|
|
TCO Temp final Boise Chamber Commerce. Verify GFI drinking fountain and front reception desk. Phone #: ###-#### Inspection requested via web by Debby Pierce Water heater disconnect shall be below 6'7". Furniture shall be complete for final. TCO partial final ok
|
Final | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | FAIL |
Rock A. Hudson
|
|
|
At the end of the day if possible Phone #: ###-#### Inspection requested via web by Debby Pierce Furniture connections shall be terminated or removed for TCO. Circuit for millwork shall terminate in a box or wiring shall be complete once millwork in place. 210.8- Drinking fountains shall have GFCI protection.
|
Electrical Rough-In | 1/10/2018 | 1/10/2018 | 1/11/2018 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling rough-in. Rooms 108,138,109,110,134 Phone #: ###-#### Inspection requested via web by Debby Pierce Discussed NEC 210.71 Meeting rooms. Due to code change year and 60 day grace period requirements for new code for meeting rooms receptacles will not be enforced. Grid for rooms noted rough in ok cover
|
Electrical Rough-In | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling Inspection.
George Morris is the contact on site ###-#### Phone #: ###-#### Inspection requested via web by Debby Pierce 108, 109, 110, and138 has 2 luminaires not ready. Rest of grid rough in ok cover
|
Electrical Rough-In | 1/8/2018 | 1/8/2018 | 1/8/2018 | A | NR |
Rock A. Hudson
|
|
|
Ceiling inspection Phone #: ###-#### Inspection requested via web by Debby Pierce Complete seizmiz support of luminaires as per 300.11. Will recall when ready.
|
Electrical Rough-In | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PART |
James Ady
|
|
|
Partial Drop ceiling only Conference room and offices on West side of South hall. only Areas listed ONLY ok to cover. Did not give go ahead to do any borders other than listed areas,
|
Electrical Rough-In | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Eric Story
|
|
|
Floor box rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Floor boxes ok to cover, Talked about installing perimeter ceiling tiles A phone will be needed to main inspector in area 327.
|
Electrical Rough-In | 12/13/2017 | 12/13/2017 | 12/13/2017 | A | PASS |
Rock A. Hudson
|
|
|
Bathroom ceiling inspection Phone #: ###-#### Inspection requested via web by Debby Pierce Bathroom drop ceilings rough in ok cover
|
Electrical Rough-In | 12/7/2017 | 12/8/2017 | 12/8/2017 | P | PART |
Rock A. Hudson
|
|
|
Can lights above hard lid ceilings Phone #: ###-#### Inspection requested via web by Debby Pierce Bathroom lids not ready, shall frame in accesses for junction boxes located above hardlids. Other drop lids rough in ok cover
|
Permanent Service | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | CANC |
Rock A. Hudson
|
|
|
Service inspection for MDP and MC Inspection requested via web by Debby Pierce Wrong permit requested, service is associated with entire building. Needed ELE16-04017
|
Electrical Rough-In | 11/28/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Rock A. Hudson
|
|
|
Wall and ceiling rough-in Phone #: ###-#### Inspection requested via web by Debby Pierce Vehicle blocked in due to all entrances closed up so landscaping around perimeter could be completed. Over 30 minutes before George was able to clear path. Will call to make sure entrance and exit will remain clear. Inspection will fail if access is not available. Wall rough in ok cover
|
Conference | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | DONE |
Rock A. Hudson
|
|
|
HVAC FCU, clearances Phone #: ###-#### Inspection requested via web by Debby Pierce Discussed access to control box on HVAC units mounting in ceiling areas. NEC 110.26 states full 30"wide and 36" deep work space shall be present. As per Daryl Degrange a reduction of 24" wide and 18" deep shall be provided minimum for access. Where an individual can safely reach over walls or piping systems for access reach shall be 18" or less so as to not create a danger of over reach.
|
Electrical Rough-In | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling rough-in for exposed hallway entry Phone #: ###-#### Inspection requested via web by Debby Pierce Discussed general contractor wanting to 1 side walls with drywall. This is not allowed except for firewalls and where needed for equipment. Electrical contractor will call for any wall cover needed. Hallway and entry on east end of building ceiling to allow for insulation. Area noted rough in ok cover with insulation only.
|