Final | 3/27/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Rock A. Hudson
|
|
|
please contact Matt Burns with any questions or concerns
Thank you and have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL Final ok
|
Electrical Rough-In | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling Inspection
Please contact Matt Bruns @ ###-#### with any questions Phone #: ###-#### Inspection requested via web by JENNY EMEL Phase 2 grid rough in ok cover
|
Electrical Rough-In | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Rock A. Hudson
|
|
|
Please contact Matt Bruns with any questions
Thank you! Phone #: ###-#### Inspection requested via web by JENNY EMEL Offices 312, 313, 314, 315, conference rm 316, reception 322, admin 323, 324, work rm 325 and break rm door 326 B wall rough in ok cover
|
Final | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Rock A. Hudson
|
|
|
Request is for a final inspection for Phase I of this project. Matt Bruns will meet you at the site.
Thank you! Phone #: ###-#### Inspection requested via web by JENNY EMEL 210.71-Conference rooms floor receptacles not in yet. IECC 2015 required C405.2.1- Occupancy sencors required in all private offices, break rooms, some offices not in. TCO for phase 1- 301 thru 311, 326 thru 328 OK
|
Conference | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | DONE |
Rock A. Hudson
|
|
|
REQUESTING A TELEPHONE CONFERENCE CONCERNING QUESTIONS ON FINAL FOR THE FIRST PHASE OF THIS PROJECT - NO ON-SITE VISIT REQUIRED
PLEASE CALL MATT BRUNS @###-####
THANK YOU VERY MUCH AND HAVE A VERY WUNDERFUL DAY! Phone #: ###-#### Inspection requested via web by JENNY EMEL Discussed the need and procedure for temp or partial final for phase 1 of remodel. Informed to request a final inspection with detailed notes as to which areas needed for TCO and that I would note a partial final for the areas listed.
|
Electrical Rough-In | 1/12/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling Inspection
Contact Matt Bruns with any Questions Phone #: ###-#### Inspection requested via web by JENNY EMEL Grid rough in ok cover
|
Electrical Rough-In | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PASS |
Rock A. Hudson
|
|
|
Please contact Matt Bruns with any questions
This is a wall rough-in inspection
Thank you and have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL Called contact to discuss 210.71 he stated he was aware of requirements. Conf. rm 302 is 228 sq.ft., 6 receptacles, rm 304 is 303 sq.ft., 7 receptacles, rm 311 is 235 sq.ft. 6 receptacles, rm 316 part of phase 2. Rooms 301 thru 311 and 326 thru 328 wall rough in ok cover
|