Final | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
James Ady
|
|
|
Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Final ok
|
Final | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PART |
James Ady
|
|
|
Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Missing panel schedules on 480v panels.
|
Final | 7/16/2018 | 7/16/2018 | 7/16/2018 | P | FAIL |
James Ady
|
|
|
Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker W/P Riser room Dead, Front office receps dead. Back of wearhouse left of roll up door recep dead, occ sensors in offices, Disc. on mini splits with proper oc protection.
|
Final | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | NR |
James Ady
|
|
|
Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Office areas attached to core and shell need copleted as well as all wearhouse lighting not in leased areas and not being changed by tenant
|
Electrical Rough-In | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
James Ady
|
|
|
We need a ceiling cover, please. Tobias is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker Ceiling ok to cover
|
Electrical Rough-In | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | FAIL |
James Ady
|
|
|
we would like to request an early morning inspection for a ceiling cover. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker 336.12 2. TC cable shall not be ran outside of a raceway or cable tray except from tray to equipment.
|
Electrical Rough-In | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
James Ady
|
|
|
Tobias is the site contact Phone #: ###-#### Inspection requested via web by Stacie Tasker added walls in south office areas only ok to cover
|
Rough-In Permanent Service | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | CANC |
James Ady
|
|
|
We need an inspection for South end of C. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
|
Electrical Rough-In | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
James Ady
|
|
|
We need an inspection for South end of C. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ok to cover walls only
|
Permanent Service | 5/25/2018 | 5/25/2018 | 5/25/2018 | P | PASS |
James Ady
|
|
|
Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker p/s u/g n ok
|
Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
James Ady
|
|
|
We need a soffit inspection. Tobias is the site contact, Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker North canopy not ready. All others ok to cover
|
Electrical Rough-In | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
James Ady
|
|
|
We need a wall cover for late afternoon if possible. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Front office demizing wall
|
Electrical Rough-In | 5/4/2018 | 5/4/2018 | 5/4/2018 | P | PASS |
Rock A. Hudson
|
|
|
We need a wall rough. Tobias is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker Fire pump room wall rough in ok cover
|
Electrical Rough-In | 3/15/2018 | 3/16/2018 | 3/16/2018 | P | CANC |
James Ady
|
|
|
We need a underground inspection. Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker
|
Electrical Rough-In | 3/14/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
James Ady
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker pour back along perimeter of building only ok to cover
|
Electrical Rough-In | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PASS |
James Ady
|
|
|
We need an underground inspection, please. Site contact is Tobias. Phone #: ###-#### Inspection requested via web by Stacie Tasker perrimeter underground ok to cover
|
Electrical Rough-In | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PASS |
James Ady
|
|
|
We need a ufer inspection. Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ufer only ok
|
Electrical Rough-In | 12/8/2017 | 12/11/2017 | 12/12/2017 | P | PASS |
Daryl DeGrange
|
|
|
We need an underground inspection. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Rough-in ok cover service feeder raceways under slab, south half of Building C
|