Final | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Patton...job complete..ok to final
|
Conference | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | CANC |
Tom Saunders
|
|
|
Will be onsite at 8 am Phone #: ###-#### Inspection requested via web by Sean Patton... didnt need conference...final pushed out couple days
|
Electrical Rough-In | 1/7/2018 | 1/8/2018 | 1/8/2018 | A | PASS |
Tom Saunders
|
|
|
Ceiling inspection for cover. I will be on-site at 8:30 Phone #: ###-#### Inspection requested via web by Sean Patton...ok to cover grid
|
Electrical Rough-In | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | PASS |
Tom Saunders
|
|
|
Approval for cover on conference floor box. Phone #: ###-#### Inspection requested via web by Sean Patton....ok to cover underground for floor outlet
|
Final | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | PASS |
Mark Moncarr
|
|
|
Sean ###-#### Ok cover. Contractor added 1 outlet each on W and E wall to cover code requirement. Also added floor outlet in center of space.
|
Electrical Rough-In | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Mark Moncarr
|
|
|
Sean ###-#### Ok cover. Contractor added 1 outlet each on W and E wall to cover code requirement. Also added floor outlet in center of space.
|
Electrical Rough-In | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | CANC |
Mark Moncarr
|
|
|
New wall inspection for cover. Phone #: ###-#### Inspection requested via web by Sean Patton Re-scheduled for 12/14/17
|