Final | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Tom Saunders
|
|
|
Chad VanOrden is contact. ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce...ok to final
|
Electrical Rough-In | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Eric Story
|
|
|
Ceiling Inspection. Chad VanOrden is contact at ###-####. thanks. Phone #: ###-#### Inspection requested via web by Debby Pierce Ceiling only ok to cover
|
Electrical Rough-In | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | FAIL |
Eric Story
|
|
|
Ceiling Inspection. Geoff Hannaford is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Fixtures not supported Open J-boxes and unused openings LV wiring shall be supported off ceiling grid
|
Electrical Rough-In | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | PASS |
Eric Story
|
|
|
Terry Cushing is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Walls only, Door says 302 not 301. Ok to cover
|