Final | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Same Electric Corrections fixed final ok
|
Final | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | FAIL |
Eric Story
|
|
|
Final for Master bedroom and bathroom Phone #: ###-#### Inspection requested via web by Same Electric Arc Fault protection required for master bed lights and outlets Wet bar receptacles shall not be on bathroom receptacle circuit
|
Electrical Rough-In | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Eric Story
|
|
|
added branch circuit for heated floors. Phone #: ###-#### Inspection requested via web by Same Electric Master floor heat ok to cover
|
Electrical Rough-In | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Eric Story
|
|
|
Need OK to cover master bed coffer and steam shower. Phone #: ###-#### Inspection requested via web by Same Electric Job taken over for misc reasons, Up master bed and bath areas open (coffer and misc walls) Ok to cover
|