Final | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Eric Story
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Final ok
|
Electrical Rough-In | 3/16/2018 | 3/20/2018 | 3/20/2018 | A | PASS |
Eric Story
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Verified u/l listing and install of Solar Array system
|
Conference | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | DONE |
Eric Story
|
|
|
Pls call Barry @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Discussed raising meter and main breaker(split-bus panel will not be touch or refeed and will remain in place unless having to do work in it)
|