Final | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
James Ady
|
|
|
Jeff is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker final ok
|
Final | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PART |
James Ady
|
|
|
We need a temp occupancy for AMAT. Jeff is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker Recep dead in office and N wall. Partial final only
|
Final | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | CANC |
James Ady
|
|
|
Jeff is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
|
Final | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | NR |
James Ady
|
|
|
Jeff is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Need Egress/ Exit signs functional
|
Electrical Rough-In | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | PASS |
James Ady
|
|
|
Dave Phone #: ###-#### Remaning open office area and break room ceiling only Check Jbox cover in break room next trip out.
|
Electrical Rough-In | 5/8/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
James Ady
|
|
|
We would like to request a late PM if possible, we need a ceiling grid. Dave is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Remaning S row offices and remaning South open office area Ceiling only
|
Electrical Rough-In | 5/8/2018 | 5/8/2018 | 5/8/2018 | P | PASS |
James Ady
|
|
|
We need a ceiling grid inspection. Dave is site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker All offices except North Side of the South row.
|
Electrical Rough-In | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
James Ady
|
|
|
ceiling grid-Danny Phone #: ###-#### SW corner open offices only ok to cover
|
Electrical Rough-In | 4/20/2018 | 4/23/2018 | 4/23/2018 | P | PART |
James Ady
|
|
|
We need a Ceiling Border cover inspection. Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker large open office area only borders only Ceiling only ok
|
Electrical Rough-In | 4/11/2018 | 4/11/2018 | 4/11/2018 | A | PASS |
James Ady
|
|
|
We need a cover inspection. Dave is the contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker Bath hardlid only ok to cover
|
Electrical Rough-In | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | PASS |
James Ady
|
|
|
We need a cover inspection. Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Break room, IT room walls only ok to cover
|
Electrical Rough-In | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | PASS |
James Ady
|
|
|
We need a cover inspection, Dave is the site contact, ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker SW offices alond demizing wall, Restrooms and storage walls only ok to cover
|
Electrical Rough-In | 3/28/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
James Ady
|
|
|
We need a cover. Dave is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Fire riser room walls and ceiling, NE office, conference rooms. Walls only ok to cover
|
Electrical Rough-In | 3/26/2018 | 3/27/2018 | 3/27/2018 | P | PART |
James Ady
|
|
|
We need a wall cover, Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker East offices and South exterior walls only No Conference rooms. Floor receps needed as per 210.71
|
Electrical Rough-In | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
James Ady
|
|
|
We need a wall cover, Dave is the site contact.. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker South offices walls only. Center area beneath storage area one side only.
|
Electrical Rough-In | 3/15/2018 | 3/16/2018 | 3/16/2018 | P | PASS |
James Ady
|
|
|
We need a wall cover inspection. Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Demizing wall oneside, and west exterior walls only ok
|
Electrical Rough-In | 3/15/2018 | 3/16/2018 | 3/15/2018 | P | CANC |
James Ady
|
|
|
We need a wall cover inspection. Tobias is the site contact. Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
|
Electrical Rough-In | 3/2/2018 | 3/5/2018 | 3/5/2018 | A | PASS |
James Ady
|
|
|
We need a underground inspection. Dave is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker underground only ok to cover
|