Final | 9/19/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
James Ady
|
|
|
Contact is Jeremiah Goins Phone #: ###-#### Inspection requested via web by Scott Campbell Final ok
|
Final | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | PART |
James Ady
|
|
|
Contact is Jeremiah Goins Phone #: ###-#### Inspection requested via web by Scott Campbell Phase 2 partial final ok
|
Electrical Rough-In | 8/29/2018 | 8/30/2018 | 8/30/2018 | P | PASS |
Rock A. Hudson
|
|
|
Jeremiah Goins is the contact Phone #: ###-#### Inspection requested via web by Scott Campbell Offices, wellness walls and hall hardlid rough in ok cover
|
Final | 8/16/2018 | 8/17/2018 | 8/17/2018 | P | PART |
James Ady
|
|
|
part final-Jermeri Phone #: ###-#### Partial final Area "B" only ok
|
Electrical Rough-In | 8/9/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
James Ady
|
|
|
CONTACT IS ANDY CHAMBERS Phone #: ###-#### Inspection requested via web by Scott Campbell East end drop ceiling and N hall to corner only ok to cover
|
Electrical Rough-In | 8/2/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
James Ady
|
|
|
Contact is Jeremiah Goins Phone #: ###-#### Inspection requested via web by Scott Campbell Will leave tile out around 5 TV locations and all cubical power drops. Ceiling only. OK to cover SE End only
|
Electrical Rough-In | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Eric Story
|
|
|
Contact is Jeremy Goins Phone #: ###-#### Inspection requested via web by Scott Campbell 6th floor womens bathroom walls and hard lids only ok to cover
|
Electrical Rough-In | 5/3/2018 | 5/7/2018 | 5/7/2018 | A | PASS |
James Ady
|
|
|
Contact is Jeremiah Goins Phone #: ###-#### Inspection requested via web by Scott Campbell Walls only area "A". ok to cover
|
Electrical Rough-In | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
James Ady
|
|
|
Contact is Jeremiah Goins Phone #: ###-#### Inspection requested via web by Scott Campbell E side 7th floor 3 offices N and 3 offices S. W side 7th floor 5 offices S. Walls only ok to cover
|