Final | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jamie berg Final ok
|
Electrical Rough-In | 6/1/2018 | 6/4/2018 | 6/4/2018 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jamie berg rough in ok
|
Final | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | CANC |
James Ady
|
|
|
Check wiring passing through trusses. ###-####
|
Electrical Rough-In | 5/16/2018 | 5/16/2018 | 5/16/2018 | A | FAIL |
James Ady
|
|
|
Check wiring passing through trusses. ###-#### Wiring passing through trusses. Re-inspect after engineer addresses issue.
|
Electrical Rough-In | 5/15/2018 | 5/15/2018 | 5/15/2018 | A | CANC |
James Ady
|
|
|
Check wiring passing through trusses. ###-####
|
Rough-In Permanent Service | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jamie berg rough in ok p/s u/g n ok
|