Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberELE18-01206
StatusFinaled
Name LEA ELECTRIC LLC
Site Address 8000 S FEDERAL WAY
Project NameC30616 B37 Office Building
Customer Number3804
ePlanReviewNo
Description
New: Complete Electrical Installation for Micron B37, including Gear, Generator, wiring, conduit, receptacles, lighting, lighting controls, fire alarm, telecomm, and security
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final1/28/20191/29/20191/29/2019APASS
DetailsJames Ady
Please call Bobby for final inspection of B37 underground. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Final ok
Final12/6/201812/7/201812/7/2018APART
DetailsJames Ady
Final for underground. Phone #: ###-#### Inspection requested via web by Rafael Castillo Partial final ok. Final permit when ELE18-04637 is complete. Underground on this permit only and associated with 1st floor underfloor wiring method.
Final12/5/201812/5/201812/5/2018PFAIL
DetailsJames Ady
Please call Bobby to walk through 1st phase partial final of 3rd floor and area C on all levels. Phone #: ###-#### Inspection requested via web by Rafael Castillo North half only. Cubicals missing blank, receps not working, reversed polarity and open nuetral. Informed electrician, will not inspect South side untill issues corrected.
Final11/30/201811/30/201811/30/2018ACANC
DetailsJames Ady
Please call Bobby for part final inspections of the 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Electrical Rough-In11/30/201811/30/201811/30/2018PPASS
DetailsJames Ady
Please call Bobby for part final inspections of the 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Please call Bobby for part final inspections of the 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Corrections on 3rd floor area A ok. 2nd floor area A tested and ready for furniture install.
Final11/29/201811/29/201811/29/2018PPART
DetailsJames Ady
Please call Bobby for lobby high ceiling inspection on 1st floor and to begin final inspections of 3rd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Misc receps not working along exterior walls. Circuit NL3B2A-17 not working. Recep under TV in room 303V dead. Informed Contractor no final will be giving untill cubicals are comple and functional as per 110.3B.
Electrical Rough-In11/27/201811/27/201811/27/2018PPART
DetailsJames Ady
Please call Bobby for inspection of linear fixtures in wooden ceiling. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Partial lobby ceiling ok to cover
Electrical Rough-In11/20/201811/20/201811/20/2018PPASS
DetailsJames Ady
Please call Bobby for inspection of 2nd floor hard lid. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor hard lid and Area B drop. ok to cover
Electrical Rough-In11/15/201811/15/201811/15/2018PPASS
DetailsJames Ady
Please call Bobby for inspection of hard lid and grid ceilings on 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area A drop ceiling and restroom hardlids ok to cover
Electrical Rough-In11/13/201811/14/201811/14/2018APASS
DetailsJames Ady
Please call Bryant for inspection of hard lid in area A 2nd floor and raised floor on 1st floor area B. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Areas listed ok to cover plus 2 offices in East corner of 1st floor. walls only
Electrical Rough-In11/8/201811/9/201811/9/2018PPASS
DetailsJames Ady
Please call Bryant for inspection of 1st floor hard lids area C.Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Hard lids on soffit only ok to cover
Electrical Rough-In11/6/201811/6/201811/6/2018PPASS
DetailsJames Ady
Please call Bryant for inspection of stair 1. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed ok to cover
Electrical Rough-In11/2/201811/2/201811/2/2018PPASS
DetailsJames Ady
Please call Bryant for wall and ceiling hard lid inspections on 1st and 2nd floor.
Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Walls only Shaft walls ok to cover
Permanent Service10/30/201810/31/201810/31/2018APASS
DetailsJames Ady
Call Cody for energizing of main gear, doors and panic hardware to be in place. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Doors and hardware installed. Permanent Service ok
Electrical Rough-In10/30/201810/30/201810/30/2018PPASS
DetailsJames Ady
Please call Bryant for ceiling grid inspection of 3rd floor area B and miscellaneous hard lids on 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Temp lighting still in place. Will need to make sure removed. Areas listed ceiling only ok to cover
Rough-In Permanent Service10/27/201810/29/201810/29/2018AFAIL
DetailsJames Ady
Please call Rafael for permanent service connection to site utility, inspection of building steel ground and gear in E301 and E302. R/I inspection of misc shaft walls. Phone #: ###-#### Inspection requested via web by Rafael Castillo 110.26C3. Personel doors and hardware shall be installed prior to energize. As per Jason Blais.
Electrical Rough-In10/26/201810/26/201810/26/2018PPART
DetailsRock A. Hudson
Please call Bobby for inspection of ceiling grid in area A of third floor and for R/I inspection of walls on 3rd floor area C. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo
Checked electrical rooms on level 3. Informed panic hardware required prior to energizing.
No walls in area C level 3 were inspected.
Level 3 area A grid only rough in ok after temp wiring has been removed.
Permanent Service10/24/201810/24/201810/24/2018PCANC
DetailsJames Ady
Please call Chris to discuss permanent power inspection. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Conference10/24/201810/24/201810/24/2018PDONE
DetailsJames Ady
Please call Chris to discuss permanent power inspection. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Talked about requirments of 230.95C. On site preformance testing. 110.26C3 Personel doors and hardware.( Panic hardware not reequired for perm service but shall be installed as soon as possible. No final without hardware in place.)
Electrical Rough-In10/22/201810/23/201810/23/2018PPASS
DetailsJames Ady
Call Bryant for inspection of 1st floor walls and raised floors. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Misc area walls 1st floor Mens hard lid 3rd floor only ok to cover
Electrical Rough-In10/18/201810/18/201810/18/2018PPASS
DetailsJames Ady
R/I inspection for underground of site lighting. Call Chris for any questions. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed ok to cover
Electrical Rough-In10/17/201810/17/201810/17/2018PPASS
DetailsJames Ady
Please call Bobby for inspection of 1st floor area C walls. Also please call Chris for underground inspection of site lighting on north end of the building. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed walls and underground only ok to cover
Electrical Rough-In10/12/201810/12/201810/12/2018PPASS
DetailsJames Ady
Please call Chris for underground R/I at B37 site. Pictures will be made available if needed. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Parking lot underground ok to cover
Electrical Rough-In10/9/201810/10/201810/10/2018PPASS
DetailsJames Ady
Please call Bryant for inspection of area B/C raised floor on 2nd floor. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo area listed raised floor only ok to cover
Electrical Rough-In10/8/201810/8/201810/8/2018PPASS
DetailsJames Ady
Please call Bryant for inspection of 3rd floor hard lid ceiling at break room and miscellaneous walls on 2nd and 3rd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Misc walls level 2 and Break room ceiling level 3
Electrical Rough-In10/4/201810/4/201810/4/2018PPASS
DetailsJames Ady
Please call Bryant for inspection of 1st and 3rd floors area C wall R/I. As close to 2PM as possible please.
Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Areas listed and marked on print ok to cover
Electrical Rough-In9/27/20189/28/20189/28/2018PPASS
DetailsJames Ady
Call Bryant for inspection of miscellaneous walls on all floors. As close to 2PM as possible. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Restroom Hard lids on 3rd floor Shaft walls on 2nd ok to cover
Electrical Rough-In9/25/20189/26/20189/26/2018APASS
DetailsJames Ady
Please call Chris for inspection of walls on 3rd floor. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Executive breakroom ok to cover walls only
Electrical Rough-In9/19/20189/21/20189/21/2018APASS
DetailsJames Ady
Please call Bryant for inspection of 2nd floor area A raised floor. As close to 12 as possible please.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor area "A" underfloor raceways ok to cover
Electrical Rough-In9/19/20189/20/20189/20/2018APASS
DetailsJames Ady
Please call Bryant for inspection of shaft walls on the 2nd floor. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor shaft walls ok to cover
Electrical Rough-In9/13/20189/13/20189/13/2018PPASS
DetailsRock A. Hudson
###-####
North side area A-B wall rough in ok cover
Electrical Rough-In9/11/20189/12/20189/12/2018ACANC
DetailsRock A. Hudson
Please call Chris for inspection of 1st floor walls. As close to 1PM as possible please.

Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Unable to inspect job prior to crew leaving for the day. Called contact he stated OK would reschedule for next day.
Electrical Rough-In9/11/20189/11/20189/11/2018PPASS
DetailsJames Ady
Please call Chris for inspection of wall, as close to 1PM as possible please.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Recall first floor.. N Exterior wall 2nd floor and 3rd floor breakroom and 3rd floor underfloor ok to cover
Electrical Rough-In8/29/20188/30/20188/30/2018APASS
DetailsJames Ady
3rd floor raised flooring conduits, 2nd floor wall rough-in
Contact Bryant Adams
Thank you Phone #: ###-#### Inspection requested via web by Tom Betty 3rd floor raised flooring, 3rd floor restroom, Nothing on 2nd floor at this time rough in ok
Electrical Rough-In8/22/20188/23/20188/23/2018APASS
DetailsJames Ady
Please call Chris for inspection of raised floor raceways and boxes. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo SW corner coduits in raised floor only ok to cover
Electrical Rough-In8/20/20188/20/20188/20/2018PPASS
DetailsJames Ady
Please call Chris for inspection of stairwell walls. As close to 11 AM as possible please.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo stairwells walls only ok to cover
Electrical Rough-In8/17/20188/20/20188/20/2018ACANC
DetailsJames Ady
Please call Chris for inspection of stairwell walls. As close to 11 AM as possible please.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo
Electrical Rough-In8/14/20188/15/20188/15/2018PPASS
DetailsJames Ady
Please call Chris for inspection of stairwell R/I. As close to 1 PM as possible please.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo talked about underfloor raceway. Stair well walls only ok to cover
Electrical Rough-In8/14/20188/14/20188/14/2018PPASS
DetailsJames Ady
Please call Chris for inspection of 3rd floor area C. Around 1 PM preferred.

Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Exterior walls, Outer walls of restrooms only, Offices in area C ok to cover
Electrical Rough-In8/9/20188/10/20188/10/2018APASS
DetailsJames Ady
Please call Bryant for inspection of shaft wall on 3rd floor area A. Sorry about this one James, only one room to look at with 2 outlets. As early as possible please, Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo ok to cover
Electrical Rough-In8/8/20188/9/20188/9/2018APASS
DetailsJames Ady
Call Chris for inspection of walls/columns on 3rd floor areas A and B. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 3rd floor Shaft walls only ok to cover
Electrical Rough-In8/7/20188/8/20188/8/2018APASS
DetailsJames Ady
Call Chris for inspection of stairwell exterior wall. As early in the AM as possible please.
Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 1st floor stairwell exterior wal and 3rd floor mens and womans restroom walls only ok
Electrical Rough-In8/2/20188/2/20188/2/2018PPASS
DetailsJames Ady
Please call Chris for inspection of walls on 3rd and 2nd floor and to look at areas where sheet rock was removed. As close to 1230 as possible please.
Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Areas on 3rd floor only ok to cover
Electrical Rough-In8/1/20188/1/20188/1/2018PPASS
DetailsJames Ady
Please call Chris for inspection of 3rd floor walls. Phone #: ###-#### Inspection requested via web by Rafael Castillo 3rd floor west side shaft walls And stair well only ok to cover
Electrical Rough-In7/19/20187/20/20187/20/2018APASS
DetailsJames Ady
Please call Chris for wall R/I inspection of 1st floor areas A ; B. As close to 11 AM as possible please.
Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Core offices as mark on print on 1st floor only, 4th floor pent house ok to cover
Electrical Rough-In7/17/20187/18/20187/18/2018PPASS
DetailsJames Ady
Please call Chris for inspection of exterior walls on 1st floor. As close to 1 PM as possible please. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 1st floor exterior walls only starting and ending at "K" line and excluding stair walls
Electrical Rough-In7/11/20187/12/20187/12/2018APASS
DetailsJames Ady
Please call Chris for inspection of 2nd floor walls. As early as possible in the morning. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor as marked on print. No shaft walls or stair ways at this time
Electrical Rough-In7/9/20187/9/20187/9/2018PPASS
DetailsJames Ady
Please call Chris for inspection of walls on 3rd floor at Micron B37. As close to 1PM as possible please. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Walls only as marked on contractors print
Conference6/26/20186/27/20186/27/2018PPASS
DetailsJames Ady
Please call Rafael to discuss cabinet enclosure for trap primer and to discuss conference/meeting room receptacle outlet requirements. As close to 1PM as possible please. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Talked about conferance room recep, inspection scheduling and recessed j box for primer recep.
Electrical Rough-In6/21/20186/21/20186/21/2018PPART
DetailsRock A. Hudson
Please call Chris for wall R/I inspection on 3rd floor in area A. As close to 1230PM as possible please. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo
As noted on contractor print rooms IT302, CO301, CO302, CO304, CO305, CO306, CO308, CO309, CO310, Wall rough in ok cover. Discussed all collaboration rooms as meeting rooms per 210.71 required receptacle outlets. Contractor to measure each meeting room and adjust for required receptacles.
Electrical Rough-In6/12/20186/12/20186/12/2018PPASS
DetailsJames Ady
Please call Rafael for inspection of last bit of underground conduit in area C. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo underground in area "C" only ok to cover
Temporary Service5/8/20185/9/20185/9/2018APASS
DetailsJames Ady
Please call Chris for inspection of temporary power service in office trailer area. As early in the morning as possible please.
Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo t/s o/h n ok
Conference5/7/20185/8/20185/8/2018PPASS
DetailsJames Ady
Please call Rafael or Chris (###-####) to discuss wiring options before roof is dried in. As close to 1230 pm as possible please.

Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed installation of Type MC cable before roof and dry sheeting. MC is outdoor rated. Installation is ok
Electrical Rough-In4/30/20185/1/20185/1/2018APASS
DetailsJames Ady
Please call Rafael for inspection of underground in area B. Phone #: ###-#### Inspection requested via web by Rafael Castillo Underground only ok to cover
Electrical Rough-In4/23/20184/24/20184/24/2018APASS
DetailsJames Ady
Please call Chris for inspection of underground in area A around electrical room 103. As close to 2:00 PM as possible please.

Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed only ok to cover
Electrical Rough-In4/18/20184/19/20184/19/2018APASS
DetailsJames Ady
Please call Chris to see further underground installation of conduit in area A. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed underground ok to cover
Electrical Rough-In4/12/20184/13/20184/13/2018PPASS
DetailsJames Ady
Please call Chris for inspection of underground in area A of slab on grade. As close to 2 pm as possible please. Thanks Phone #: ###-#### Inspection requested via web by Rafael Castillo area listed ok to cover underground only
Electrical Rough-In4/11/20184/12/20184/12/2018APASS
DetailsJames Ady
Please call Chris Gardner for underground inspection of area A slab on grade. As early in the morning as possible please. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Underground in area listed only ok to cover
Conference4/9/20184/10/20184/10/2018APASS
DetailsJames Ady
Please call Rafael to discuss Micron B37 (general installation discussion). As close to 11AM as possible (I will be in meetings in the morning from 0730 - approximately 1030). Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed underground inspection process.