Final | 8/17/2018 | 8/20/2018 | 8/20/2018 | A | PASS |
Mark Moncarr
|
|
|
###-#### Permit number issues. Only 1 permit number available for job besides temp pole. Additional permit number is 18-03131 for the TI. 18-01447 is for core and shell. Ok final core an shell. 2nd ele permit 18-03131 is for TI final.
|
Final | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | CANC |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Re-scheduled for 8/20/18
|
Permanent Service | 8/2/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Core and shell cannot be finaled until egress lighting and all exterior lts including parking lot lts are installed. p/s u/g n ok
|
Electrical Rough-In | 8/1/2018 | 8/1/2018 | 8/1/2018 | A | PASS |
Mark Moncarr
|
|
|
Ceiling inspection Phone #: ###-#### Inspection requested via web by kendall bender Ok cover all ceiling except for work room on S side, and tall ceiling in main area.
|
Electrical Rough-In | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PASS |
Mark Moncarr
|
|
|
Pole base inspection Phone #: ###-#### Inspection requested via web by kendall bender Ok cover 8 pole bases in various locations on property.
|
Electrical Rough-In | 7/30/2018 | 7/31/2018 | 7/30/2018 | A | CANC |
Mark Moncarr
|
|
|
pole base inspection please Phone #: ###-#### >> Inspection requested via web by kendall bender Inspection cancelled from web by: kendall bender
|
Electrical Rough-In | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | CANC |
Mark Moncarr
|
|
|
hard lids and soffits Phone #: ###-#### >> Inspection requested via web by kendall bender Inspection cancelled from web by: kendall bender
|
Electrical Rough-In | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Mark Moncarr
|
|
|
Underground exterior Phone #: ###-#### Inspection requested via web by kendall bender Ok cover exterior grd work for main power and drive thru.
|
Electrical Rough-In | 7/12/2018 | 7/13/2018 | 7/13/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Ok cover E wall and 2 baths.
|
Electrical Rough-In | 7/9/2018 | 7/9/2018 | 7/9/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Ok cover exterior lighting. ALL sheetrock to be removed on panel wall in SE corner. Sheetrock was installed on all exterior walls before electrical installation. For future parking lot light conduit install, ALL trenches WILL be open for ground works inspection.
|
Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Mark Moncarr
|
|
|
Under slab Phone #: ###-#### Inspection requested via web by kendall bender Ok cover underground.
|
Electrical Rough-In | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Tom Saunders
|
|
|
Ufer inspections and conduit thru footings Phone #: ###-#### Inspection requested via web by kendall bender...uffer and conduits ok to cover
|