Final | 11/6/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Rock A. Hudson
|
|
|
We need a final inspection for the canopy and parking expansion. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins Final ok
|
Electrical Rough-In | 10/12/2018 | 10/15/2018 | 10/15/2018 | A | PASS |
Tom Saunders
|
|
|
Atm canopy Phone #: ###-#### Inspection requested via web by Tom Jenkins...ok to cover..can lights and power for signage
|
Electrical Rough-In | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Eric Story
|
|
|
Pole bases and u/g to them ok to cover
|
Electrical Rough-In | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | CANC |
Jim Page
|
|
|
Pole bases Phone #: ###-#### Inspection requested via web by Tom Jenkins
|
Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Eric Story
|
|
|
uNDERGROUND Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g for parking lot ok to cover
|