Final | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PASS |
James Ady
|
|
|
shed and street light Phone #: ###-#### Inspection requested via web by cris flores Final ok
|
Final | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PART |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by cris flores 1st floor only final ok
|
Final | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PART |
James Ady
|
|
|
3rd and 2nd floor. Phone #: ###-#### Inspection requested via web by cris flore 2nd and 3rd floor only Final ok
|
Electrical Rough-In | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
James Ady
|
|
|
Bike shop wall cover lights and outlets Phone #: ###-#### Inspection requested via web by cris flores Area listed ok to cover
|
Rough-In Permanent Service | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by cris flores p/s u/g n ok
|
Electrical Rough-In | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | PASS |
James Ady
|
|
|
2nd and 3rd floor wall cover Phone #: ###-#### Inspection requested via web by cris flores Corrections made rough in ok
|
Electrical Rough-In | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | FAIL |
James Ady
|
|
|
2nd and 3rd floor Phone #: ###-#### Inspection requested via web by cris flores 3rd floor South appartment. Need recep within 6ft of balcony door. 2nd and 3rd floor North appartments, missed wires to circulating fans
|
Electrical Rough-In | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | NR |
James Ady
|
|
|
2nd and 3rd floor Phone #: ###-#### Inspection requested via web by cris flores No access Just poured concrete stair runners
|
Electrical Rough-In | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | FAIL |
Eric Story
|
|
|
Chris - 2nd and 3rd floor Phone #: ###-#### NAil plates throughout all units, Allowed insulator to fire caulk as all that needs to be verified is nailplates...
|
Electrical Rough-In | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
James Ady
|
|
|
Wall cover Phone #: ###-#### Inspection requested via web by cris flores 1st floor 3 appartments only
|
Electrical Rough-In | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
James Ady
|
|
|
Ground works sonotube Phone #: ###-#### Inspection requested via web by cris flores Underground ok to cover and light pole base
|
Electrical Rough-In | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | FAIL |
Rock A. Hudson
|
|
|
Wall cover Phone #: ###-#### Inspection requested via web by cris flores Contractor needed 3 level only, stairs not in offered man lift on front of grade all. No fall protection provided. Recall when stairs installed for access and egress from top level.
|