Final | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Eric Story
|
|
|
Final ok for all remaining units in building
|
Final | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PART |
Eric Story
|
|
|
3RD PHASE OF 6 SIX UNITS OK
|
Final | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PASS |
Eric Story
|
|
|
2nd (6) units on east building Phone #: ###-#### Inspection requested via web by Kevin Burke Discussed with appliance installers and electrician about installing pigtails on dryer and ranges. Second phase of units ok
|
Final | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PART |
Eric Story
|
|
|
POart final for first 6 units First six units ok
|
Final | 8/30/2018 | 8/30/2018 | 8/30/2018 | P | CANC |
Eric Story
|
|
|
Please call ahead before arriving. Phone #: ###-#### Inspection requested via web by Kevin Burke Res-cheduled for the moring so egress lights can be installed
|
Electrical Rough-In | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Eric Story
|
|
|
Last 6 units on north end. Phone #: ###-#### Inspection requested via web by Kevin Burke Final 6 unuts ok to cover
|
Rough-In Permanent Service | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Eric Story
|
|
|
North end service Phone #: ###-#### Inspection requested via web by Kevin Burke Rough-in ok to cover remaining 6 units p/s u/g n ok
|
Electrical Rough-In | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | PASS |
Eric Story
|
|
|
6 units of 2nd 12 plex Phone #: ###-#### Inspection requested via web by Kevin Burke Rough-in ok to cover 6 units given
|
Electrical Rough-In | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
James Ady
|
|
|
2nd set of six units on south end Phone #: ###-#### Inspection requested via web by Kevin Burke rough in ok
|
Permanent Service | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
James Ady
|
|
|
South end service of first building. Phone #: ###-#### Inspection requested via web by Kevin Burke p/s u/g n ok
|
Electrical Rough-In | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
James Ady
|
|
|
(2) light pole bases Phone #: ###-#### Inspection requested via web by Kevin Burke Underground and pole bases ok to cover
|
Electrical Rough-In | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Eric Story
|
|
|
First (6) units starting from the south. Phone #: ###-#### Inspection requested via web by Kevin Burke 1st 6 units ok to cover
|
Electrical Rough-In | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Eric Story
|
|
|
BLD #2 Soffits in stairwells, columns Phone #: ###-#### Inspection requested via web by Kevin Burke Soffits and stairs only ok to cover
|