Final | 12/20/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Stairway between 3 and 4 not done but all wiring in area associated with TI permit. Final ok
|
Final | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton BCC- Electrical permit from city of Boise required for elevator installation. 300.15- All boxes shall have covers, basement "L" shaped box and sump pump wiring. 250.30(A)(4)- The building or structure grounding electrode system shall be used for grounding seperately derived systems. Level 3 trans. Stairs from level 3 to 4 not complete nor is lighting for stairs. Will check with building inspector on this.
|
Final | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | NH |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Called contact, no answer, mail box full. Must recall when available.
|
Electrical Rough-In | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Level 1 corridor grid rough in ok cover
|
Electrical Rough-In | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton South stairway all fished in, north stairway walls and hardlids rough in ok cover
|
Permanent Service | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton p/s u/g n ok
|
Electrical Rough-In | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Level 1 bathroom hardlids rough in ok cover
|
Electrical Rough-In | 9/11/2018 | 9/12/2018 | 9/11/2018 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton 2nd and 4th floor restrooms Hard lids only ok to cover
|
Electrical Rough-In | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Rock A. Hudson
|
|
|
Bathrooms levels 1 and 4 wall rough in ok cover
|
Electrical Rough-In | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Levels 2, and 3 bathrooms walls and hard lids rough in ok cover
|
Electrical Rough-In | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Discussed new permits needed for elevator. Electrical contractor has scope included in core and shell, elevator contractor will need seperate city and state permits. Underground conduits for new gear in basement rough in ok cover.
|