Final | 10/10/2018 | 10/10/2018 | 10/10/2018 | P | PASS |
Tom Saunders
|
|
|
Job Foreman Jay Karel Phone #: ###-#### Inspection requested via web by Laurie Hoelscher...UL listing and disconnect verified
|
Final | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PEND |
Tom Saunders
|
|
|
Early as possible please -Crew needs to be off site by 10:00 am. Phone #: ###-#### Inspection requested via web by Laurie Hoelscher...contractor rep Drew ###-#### stated job complete...pillar lights being installed by others...others will need to pull permit for work..will final permit once verified permit pulled by others
|
Electrical Rough-In | 8/28/2018 | 8/29/2018 | 8/28/2018 | A | PASS |
Tom Saunders
|
|
|
Early as possible please -Crew needs to be off site by 10:00 am. Phone #: ###-#### Inspection requested via web by Laurie Hoelscher...rooftop work verified by pictures-junctions for new pillar lights, blanking off light boxes at signage...boxes installed with blanks on pillar light locations
|