Permanent Service | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
James Ady
|
|
|
call half hour before to meet there // Richard Phone #: ###-#### p/s u/g rec ok
|
Final | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | NR |
James Ady
|
|
|
I''ve added two eight foot grounding rods 6 feet apart with #4 copper wire connecting them to the service meter. I have not connected the wire into the panel--leaving that for my electrician when he comes to do the cut-over with Idaho Power. I have left an ample length of #4 wire from the grounding rods to the service meter. I''ve also flipped the expansion coupler over so that it''s now correctly oriented. Please call if you have any questions ###-#### thank you, Dru Phone #: ###-#### Inspection requested via web by Dru Nakaya Spoke with contractor, He wiil schedule inspection when he is ready
|
Rough-In Permanent Service | 11/1/2018 | 10/31/2018 | 11/1/2018 | P | FAIL |
James Ady
|
|
|
I set a new meter panel and underground conduit, per Idaho Power''s specifications, so that Idaho Power can remove my overhead power and run service underground. Phone #: ###-#### Inspection requested via web by Dru Nakaya 250.50 All services shall have a grounding electrode system. 110.3. All instalations per manu. instructions( Slip joint on riser is upside down.
|
Electrical Rough-In | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
James Ady
|
|
|
I set a new meter panel and underground conduit, per Idaho Power''s specifications, so that Idaho Power can remove my overhead power and run service underground. equested via web by Dru Nakaya ID power trench ok to cover
|